Permit: T08CM02591
Permit Details
Apply Date:
07/28/2008
Applicant:
U S SALES COMPANY L L C
Description:
SFR:TD16-91-11 T07-M0103
Contractors:
- U S SALES COMPANY L L C
Permit Reviews
Permit Number - T08CM02591
Permit Status: C of o
Permit Description: SFR:TD16-91-11 T07-M0103
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/28/2008 | RESIDENTIAL BLDG-MODEL PLAN/ENGINE/WALK THRU | 07/28/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM02591
Permit Status: C of o
Permit Description: SFR:TD16-91-11 T07-M0103
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/28/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM02591
Permit Description: SFR:TD16-91-11 T07-M0103
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/02/2008 | PLUMBING - SEWER HCS CONNECT | CRUIZ | Approved | IVRS - Inspection :* |
| 10/02/2008 | PLUMBING - ROUGH, SOIL | CRUIZ | Approved | IVRS - Inspection :* |
| 11/04/2008 | ELECTRIC - UFER | CRUIZ | Approved | |
| 11/04/2008 | BUILDING PRE-SLAB | CRUIZ | Approved | IVRS - Inspection :* |
| 11/04/2008 | EXCAVATION/LAYOUT REBAR & ZON | CRUIZ | Approved | IVRS - Inspection :* |
| 12/17/2008 | ROOF NAILING | CRUIZ | Approved | IVRS - Inspection :* |
| 12/17/2008 | EXT METAL CLIPS/EXT SHEATHING | CRUIZ | Approved | IVRS - Inspection :* |
| 01/16/2009 | PLUMBING - YARD WTR LINE/TEST | CRUIZ | Approved | IVRS - Inspection :* |
| 01/22/2009 | MECHANICAL - INTERMEDIATE | CRUIZ | Approved | IVRS - Inspection :* |
| 01/22/2009 | PLUMBING - INTERMEDIATE | CRUIZ | Approved | IVRS - Inspection :* |
| 01/22/2009 | ELECTRIC - TEMPORARY SERVICE | CRUIZ | Approved | IVRS - Inspection :* |
| 01/22/2009 | ELECTRIC - CABLE DROP | CRUIZ | Approved | IVRS - Inspection :* |
| 01/22/2009 | U VALUE FOR WINDOW | CRUIZ | Approved | IVRS - Inspection :* |
| 01/23/2009 | STUCCO MESH | CRUIZ | Approved | IVRS - Inspection :* |
| 01/23/2009 | FRAMING | CRUIZ | Approved | IVRS - Inspection :* |
| 01/23/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER C. RUIZ |
| 01/27/2009 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 02/02/2009 | SHEET ROCK NAILING | CRUIZ | Approved | IVRS - Inspection :* |
| 05/12/2009 | PLUMBING - FINAL | CRUIZ | Approved | IVRS - Inspection :* |
| 05/12/2009 | ELECTRIC - FINAL | CRUIZ | Approved | IVRS - Inspection :* |
| 06/18/2009 | MECHANICAL - FINAL | WNORTH | Approved | IVRS - Inspection :* |
| 06/24/2009 | BUILDING - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 06/25/2009 | PERMIT FINALED | JWEATHER | Approved |