Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T08CM02439
Permit Details
Apply Date:
07/11/2008
Applicant:
N/A
Description:
TELECOM CELL TOWER SITE (SHADE STRUCTURE AND TOWER)
Contractors:
- WALLEN COMMUNICATIONS L L C
Permit Reviews
Permit Number - T08CM02439
Permit Status: Si_xpire
Permit Description: TELECOM CELL TOWER SITE (SHADE STRUCTURE AND TOWER)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/11/2008 | PLANS OK TO SUBMIT - COMM | 07/14/2008 | COMPLETED |
| 07/14/2008 | RESUBMITTAL | 07/14/2008 | COMPLETED |
| 07/14/2008 | RESUBMITTAL | 08/01/2008 | COMPLETED |
| 08/08/2008 | RESUBMITTAL | 08/27/2008 | COMPLETED |
| 08/27/2008 | RESUBMITTAL | 09/11/2008 | COMPLETED |
| 08/28/2008 | SITE | 09/11/2008 | COMPLETED |
| 09/11/2008 | RESUBMITTAL | 09/25/2008 | COMPLETED |
| 09/25/2008 | RESUBMITTAL | 09/25/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM02439
Permit Status: Si_xpire
Permit Description: TELECOM CELL TOWER SITE (SHADE STRUCTURE AND TOWER)
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 07/11/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 07/14/2008 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. |
Completed Inspections
Permit Status: Si_xpire
Permit Number: T08CM02439
Permit Description: TELECOM CELL TOWER SITE (SHADE STRUCTURE AND TOWER)
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/14/2008 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* |
| 10/20/2008 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* |
| 11/02/2008 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* |
| 11/02/2008 | ELECTRIC - UFER | RJIROUDE | Approved | IVRS - Inspection :* |
| 11/04/2008 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
| 11/05/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER R. JIROUDEK |
| 01/12/2009 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
| 01/12/2009 | ENGINEERING - FINAL | JBRUCKME | Approved | |
| 01/12/2009 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
| 01/12/2009 | BUILDING - PROGRESS | GDABBS | Approved | IVRS - Inspection :* |
| 01/12/2009 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
| 01/12/2009 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
| 01/12/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 01/12/2009 | NPPO - FINAL | ACONNOR | Approved | |
| 01/12/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 01/13/2009 | FIRE - FINAL | LTHOMAS | Approved | |
| 07/15/2009 | PERMIT FINALED | LJACKSON | Approved |