Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T08CM02233
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
4210 N 1ST AV #100
Address NEW:
4210 N 1ST AV #100
Apply Date:
06/24/2008
Applicant:
N/A
Description:
TI:YOGURT SHOP
Architects:
- PARAGON ARCHITECTS LLC
Contractors:
- CHESTNUT CONSTRUCTION CORPORATIO
Permit Reviews
Permit Number - T08CM02233
Permit Status: C of o
Permit Description: TI:YOGURT SHOP
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/24/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 06/25/2008 | COMPLETED |
| 06/25/2008 | 3RD PARTY REVIEW-COMMERCIAL TI | 08/05/2008 | COMPLETED |
| 08/05/2008 | POST 3RD PARTY REVIEW | 10/01/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM02233
Permit Status: C of o
Permit Description: TI:YOGURT SHOP
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/24/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM02233
Permit Description: TI:YOGURT SHOP
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/12/2008 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* ABS DWV UNDERSLAB OK TO COVER WATER TEST ONE RISER TO TEN FEET OK |
| 09/19/2008 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* THE LATERAL BRACING FOR THE CLOUD CANNOT BE SECURED TO THE DUCT WORK, MOVE TO STRUCTURE |
| 09/19/2008 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 09/21/2008 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 09/24/2008 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
| 09/24/2008 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/17/2008 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* CLOSET FLANGES OK |
| 10/21/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | TMPP CLEARED FOR #100 PER R. HOLLANDER |
| 10/31/2008 | RIGHT OF WAY - FINAL | MOTERO | Approved | |
| 10/31/2008 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :$ |
| 10/31/2008 | NPPO - FINAL | ACONNOR | Approved | |
| 10/31/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 10/31/2008 | FIRE - FINAL | LTHOMAS | Approved | |
| 10/31/2008 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 11/04/2008 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | |
| 11/04/2008 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* PLUMBING FINAL OK SUBJECT TO CLEAN BACTERIA REPORT |
| 11/04/2008 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 11/04/2008 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
| 11/04/2008 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
| 11/04/2008 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 11/05/2008 | FRAMING | LHANLY | Approved | |
| 11/05/2008 | BUILDING - FINAL | LHANLY | Approved | |
| 11/06/2008 | SIGN - FINAL | JYBARRA | Approved |