Permit: T08CM00876
Permit Details
Apply Date:
03/17/2008
Applicant:
GABE LARA
Description:
TI: SALON
Contractors:
- A L SANTA MARIA DESIGN AND CONSTRUCT
Permit Reviews
Permit Number - T08CM00876
Permit Status: C of o
Permit Description: TI: SALON
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/18/2007 | PLANS OK TO SUBMIT - 3RD PARTY | 03/19/2008 | COMPLETED |
03/19/2008 | 3RD PARTY REVIEW-COMMERCIAL TI | 04/21/2008 | COMPLETED |
04/21/2008 | POST 3RD PARTY REVIEW | 05/07/2008 | COMPLETED |
05/27/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 05/27/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM00876
Permit Status: C of o
Permit Description: TI: SALON
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/17/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM00876
Permit Description: TI: SALON
Total Completed Inspections - 30
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/15/2008 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
06/03/2008 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
06/09/2008 | FRAMING | JBURGE | Approved | IVRS - Inspection :* OK TO ONE SIDE SHEETROCK PENDING ELECTRIC & PLUMBING INTERMEDIATES *SLIP TRACK QUESTION ADDRESSED BY LETTER FROM ARCHITECT DATED 5 JUNE 2008 |
06/09/2008 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* OK TO SHEETROCK #100-101 |
06/20/2008 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* PVC YARDWATER INSTALLED OK OK TO COVER WITH CLEAN FILL DON'T FORGET TO TAPE COPPER PASSING THRU MASONRY |
06/25/2008 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
06/25/2008 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
07/01/2008 | MECHANICAL - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
07/01/2008 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
07/01/2008 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
07/01/2008 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
07/07/2008 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
07/23/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR 'M' & 'M2' PER D. SANTACRUZ |
07/29/2008 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
07/29/2008 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
07/29/2008 | NPPO - FINAL | ACONNOR | Approved | |
07/29/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | |
07/30/2008 | FIRE - FINAL | DRAMIREZ | Approved | Approved 7/30/08. |
07/30/2008 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
07/30/2008 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
07/30/2008 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
07/31/2008 | MECHANICAL - FINAL | MRAMBER | Approved | PER INSP CARD |
07/31/2008 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
07/31/2008 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* |
07/31/2008 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* |
07/31/2008 | BUILDING - PROGRESS | MHENSON | Approved | IVRS - Inspection :* |
07/31/2008 | U VALUE FOR WINDOW | MHENSON | Approved | IVRS - Inspection :* |
07/31/2008 | ENGINEERING - FINAL | NKALAHAR | Approved | WATER METER WORK ON COUNTRY CLUB NOT ASSOCIATED WITH THIS PROJECT RAMP IS AT 7.7% |
07/31/2008 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
07/31/2008 | ELECTRIC - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |