Permit: T08CM00436
Permit Details
Apply Date:
02/07/2008
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEW RETAIL SHELL BLDG MAJOR 5
Contractors:
- GILES CONSTRUCTION INC ,
Permit Reviews
Permit Number - T08CM00436
Permit Status: Final
Permit Description: NEW RETAIL SHELL BLDG MAJOR 5
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/07/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 02/07/2008 | COMPLETED |
02/07/2008 | 3RD PARTY REVIEW-COMMERCIAL | 05/22/2008 | COMPLETED |
05/22/2008 | POST 3RD PARTY REVIEW | 06/10/2008 | COMPLETED |
06/10/2008 | RESUBMITTAL | 08/26/2008 | COMPLETED |
07/28/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 07/30/2008 | COMPLETED |
08/26/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 08/28/2008 | COMPLETED |
09/12/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 09/15/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM00436
Permit Status: Final
Permit Description: NEW RETAIL SHELL BLDG MAJOR 5
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/07/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T08CM00436
Permit Description: NEW RETAIL SHELL BLDG MAJOR 5
Total Completed Inspections - 36
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/22/2008 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :* INCOMPLETE |
09/16/2008 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* EXCLUDES STORE FRONT |
09/17/2008 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
10/06/2008 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* ON STORE FRONT |
10/10/2008 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
10/15/2008 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection :* |
10/21/2008 | STUCCO MESH | MHENSON | Approved | IVRS - Inspection :* |
10/30/2008 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
10/31/2008 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* DUMPSTER TOP OUT |
11/05/2008 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | IVRS - Inspection :* |
11/05/2008 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
11/05/2008 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
11/05/2008 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
11/06/2008 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection :* |
11/06/2008 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
11/06/2008 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
11/06/2008 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
11/07/2008 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
11/07/2008 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | IVRS - Inspection :* |
11/07/2008 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
11/07/2008 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
11/07/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | |
11/07/2008 | EXCAVATION/LAYOUT REBAR & ZON | IVR USER | Approved | IVRS - RI canceled |
11/10/2008 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | |
11/12/2008 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | |
11/12/2008 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | |
11/12/2008 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
11/12/2008 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
11/14/2008 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
11/19/2008 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
11/19/2008 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
11/19/2008 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
11/19/2008 | FIRE - FINAL | LTHOMAS | Approved | |
11/25/2009 | PERMIT FINALED | MHENSON | Approved | |
11/25/2009 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* 1) NO C OF O, LETTER OF COMPLETION ONLY |
11/25/2009 | ENGINEERING - FINAL | MCARREON | Approved | PUNCH LIST ITEMS HAVE BEEN ADDRESSED. OKAY TO RELEASE SHELL. ANY FUTURE ITEMS OF CONCERN WILL BE ON CM PERMIT. |