Permit: T08CM00391
Permit Details
Status:
Final
Type:
COMMERCIAL NEW
Address:
3955 E FORT LOWELL RD
Address NEW:
3955 E FORT LOWELL RD
Apply Date:
02/05/2008
Applicant:
N/A
Description:
NEW SHELL OFFICE BUILDING
Architects:
- CHAVEZ, MARIO SALAS
Contractors:
- RIO WEST DEVELOPMENT AND CONSTR *C*
Permit Reviews
Permit Number - T08CM00391
Permit Status: Final
Permit Description: NEW SHELL OFFICE BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/05/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 02/05/2008 | COMPLETED |
| 02/05/2008 | 3RD PARTY REVIEW-COMMERCIAL | 03/26/2008 | COMPLETED |
| 03/27/2008 | POST 3RD PARTY REVIEW | 04/03/2008 | COMPLETED |
| 04/03/2008 | RESUBMITTAL | 04/03/2008 | COMPLETED |
| 07/21/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 09/30/2008 | COMPLETED |
| 09/30/2008 | 3RD PARTY REVIEW-REVISION/OTHER-2ND | 10/07/2008 | COMPLETED |
| 11/13/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 11/14/2008 | COMPLETED |
| 11/18/2008 | RESUBMITTAL | 11/19/2008 | COMPLETED |
| 12/16/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 05/06/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM00391
Permit Status: Final
Permit Description: NEW SHELL OFFICE BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/05/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T08CM00391
Permit Description: NEW SHELL OFFICE BUILDING
Total Completed Inspections - 41
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/21/2008 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* BLDG "4" EAST & WEST -- OK TO POUR CONTINUOUS FOOTING AND COLUMN FOOTINGS |
| 05/02/2008 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 05/14/2008 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | Need flush |
| 05/23/2008 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
| 05/28/2008 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* WEST PORTION OF BUILDING - OK TO POUR SLAB |
| 08/19/2008 | FRAMING | JBURGE | Approved | IVRS - Inspection :* BLDG. 4 WEST |
| 08/19/2008 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* BLDG. 4 WEST OK TO COVER |
| 08/26/2008 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 08/26/2008 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 08/26/2008 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 08/26/2008 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* |
| 09/11/2008 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* 1. OK U.G RACEWAYS FROM TEP XFMR TO SES LOCATIONS 2. OK U.G RACEWAYS FOR TELEPHONE 3. INSTALL WARNING RIBBON PER NEC 300.5 |
| 10/08/2008 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 10/20/2008 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* SCREEN WALL @ 12' - TOPPED OUT; BETWEEN EAST & WEST BUILDINGS -- OK TO GROUT |
| 11/21/2008 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* BLDG'S EAST & WEST |
| 11/25/2008 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* YARD WATER OK NEED TO SEE CONN. TO RP AND METER |
| 01/08/2009 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
| 01/08/2009 | SIGN - FINAL | JYBARRA | Approved | SHELL ONLY |
| 01/09/2009 | NPPO - FINAL | ACONNOR | Approved | |
| 01/09/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 01/16/2009 | PLUMBING - ROOF DRAINS | BBENEDON | Approved | IVRS - Inspection :* |
| 02/03/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR "OWNERS PANELS-METERS #1 & 2" PER R. MORENO |
| 02/06/2009 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 02/11/2009 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 02/20/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* OK FOR SHELL FINAL |
| 02/20/2009 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 02/20/2009 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 02/20/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 03/24/2009 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
| 04/20/2009 | OUTDOOR LIGHTING FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 04/20/2009 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 04/20/2009 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | IVRS - Inspection :* |
| 04/21/2009 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | |
| 04/21/2009 | ELECTRIC - TEMPORARY SERVICE | RMORENO | Approved | |
| 04/21/2009 | ELECTRIC - UFER | RMORENO | Approved | |
| 04/23/2009 | FIRE - FINAL | LTHOMAS | Approved | |
| 04/23/2009 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 04/30/2009 | ENGINEERING - FINAL | JBRUCKME | Approved | |
| 04/30/2009 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 04/30/2009 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 04/30/2009 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |