Permit Reviews
Permit Number - T08CM00253
Permit Status: Final
Permit Description: NEW SFR
R1 Truss Design
R3 CHANGE GARAGE TO LIVING SPACE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/24/2008 | RESIDENTIAL BLDG/ZONING/ENGINE/WWM | 01/24/2008 | COMPLETED |
| 01/24/2008 | RESIDENTIAL BLDG/WWM | 02/21/2008 | COMPLETED |
| 02/27/2008 | RESUBMITTAL | 04/23/2008 | COMPLETED |
| 05/28/2008 | REVISION - - 1ST | 06/16/2008 | COMPLETED |
| 06/04/2008 | REVISION - - 2ND | 06/14/2008 | COMPLETED |
| 11/20/2008 | REVISION - - 3RD | 12/31/2008 | COMPLETED |
| 12/31/2008 | REVISION - - 3RD | 12/31/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM00253
Permit Status: Final
Permit Description: NEW SFR
R1 Truss Design
R3 CHANGE GARAGE TO LIVING SPACE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/24/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T08CM00253
Permit Description: NEW SFR
R1 Truss Design
R3 CHANGE GARAGE TO LIVING SPACE
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/07/2008 | PLUMBING - SEWER HCS CONNECT | DWALKER | Approved | IVRS - Inspection :* |
| 05/07/2008 | PLUMBING - YARD WTR LINE/TEST | DWALKER | Approved | IVRS - Inspection :* |
| 05/07/2008 | PLUMBING - ROUGH, SOIL | DWALKER | Approved | IVRS - Inspection :* |
| 05/09/2008 | STEM WALL/RETAINING WALL | DWALKER | Approved | IVRS - Inspection :* NEED HOLDDOWNS IN PLACE OR RETRO'S AT FRAMING INSPECTIONS |
| 05/09/2008 | EXCAVATION/LAYOUT REBAR & ZON | DWALKER | Approved | IVRS - Inspection :* |
| 05/09/2008 | BUILDING PRE-SLAB | DWALKER | Approved | IVRS - Inspection :* |
| 05/09/2008 | ELECTRIC - UFER | DWALKER | Approved | IVRS - Inspection :* |
| 06/25/2008 | MECHANICAL - INTERMEDIATE | DWALKER | Approved | CHANGED FROM AP TO PARTIAL PER C. TREVILLYAN 12/31/08 |
| 06/25/2008 | PLUMBING - INTERMEDIATE | DWALKER | Approved | IVRS - Inspection :* |
| 06/25/2008 | PLUMBING - PRE SLAB | DWALKER | Approved | IVRS - Inspection :* |
| 06/25/2008 | U VALUE FOR WINDOW | DWALKER | Approved | IVRS - Inspection :* |
| 06/27/2008 | FRAMING | DWALKER | Approved | CHANGED FROM AP TO PARTIAL PER C. TREVILLYAN 12/31/08 |
| 06/27/2008 | ELECTRIC - INTERMEDIATE | DWALKER | Approved | CHANGED FROM AP TO PARTIAL PER C. TREVILLYAN 12/31/08 |
| 06/27/2008 | STUCCO MESH | DWALKER | Approved | IVRS - Inspection :* |
| 06/27/2008 | ROOF NAILING | DWALKER | Approved | IVRS - Inspection :* |
| 06/27/2008 | EXT METAL CLIPS/EXT SHEATHING | DWALKER | Approved | IVRS - Inspection :* |
| 07/10/2008 | ELECTRIC - FINAL | DWALKER | Approved | IVRS - Inspection :* |
| 07/31/2008 | SHEET ROCK NAILING | DWALKER | Approved | CHANGED FROM AP TO PARTIAL PER C. TREVILLYAN 12/31/08 |
| 08/05/2008 | ELECTRIC - TEMPORARY SERVICE | DWALKER | Approved | IVRS - Inspection :* |
| 08/05/2008 | ELECTRIC - CABLE DROP | DWALKER | Approved | IVRS - Inspection :* |
| 08/06/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER D. WALKER |
| 08/12/2008 | ASSURANCE | MCARREON | Approved | |
| 02/04/2009 | MECHANICAL - FINAL | DWALKER | Approved | IVRS - Inspection :* |
| 02/04/2009 | PLUMBING - FINAL | DWALKER | Approved | IVRS - Inspection :* |
| 02/04/2009 | BUILDING - FINAL | DWALKER | Approved | IVRS - Inspection :* |
| 02/05/2009 | PERMIT FINALED | BFLORES | Approved |