Permit: T07CM04140
Permit Details
Apply Date:
10/22/2007
Applicant:
WATSON, JAMES RICHARD
Description:
NEW P H CONTROL SYSTEM FOR WASTEWATER
Architects:
- WATSON, JAMES RICHARD
Contractors:
- PARRISH CONSTRUCTION COMPANY ,
Permit Reviews
Permit Number - T07CM04140
Permit Status: Final
Permit Description: NEW P H CONTROL SYSTEM FOR WASTEWATER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/04/2008 | REVISION - SITE | 01/04/2008 | COMPLETED |
| 10/22/2007 | PLANS OK TO SUBMIT - 3RD PARTY | 10/22/2007 | COMPLETED |
| 10/22/2007 | PLANS OK TO SUBMIT - SITE | 10/22/2007 | COMPLETED |
| 10/22/2007 | SITE | 11/15/2007 | COMPLETED |
| 10/22/2007 | 3RD PARTY REVIEW-COMMERCIAL TI | 11/09/2007 | COMPLETED |
| 11/09/2007 | POST 3RD PARTY REVIEW | 11/15/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM04140
Permit Status: Final
Permit Description: NEW P H CONTROL SYSTEM FOR WASTEWATER
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/22/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T07CM04140
Permit Description: NEW P H CONTROL SYSTEM FOR WASTEWATER
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/21/2007 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* |
| 11/21/2007 | STEM WALL/RETAINING WALL | GDABBS | Approved | IVRS - Inspection :* |
| 11/21/2007 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* |
| 11/29/2007 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* |
| 12/05/2007 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
| 12/05/2007 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 12/17/2007 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
| 12/17/2007 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 12/17/2007 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 12/20/2007 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* PIPING FROM PUMP STATION TO TANK TEST 4" OK |
| 12/27/2007 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/27/2007 | SITE - SEWER | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/31/2007 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* CALL FOR FINAL AFTER POWER CK |
| 01/03/2008 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
| 01/08/2008 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 01/08/2008 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 01/17/2008 | FIRE - FINAL | CSCHULTZ | Approved | |
| 01/17/2008 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
| 02/01/2008 | PLUMBING - FINAL | RLEDONNE | Approved | |
| 07/30/2008 | PERMIT FINALED | LJACKSON | Approved |