Permit: T07CM03775
Permit Details
Apply Date:
09/18/2007
Applicant:
FAST PERMITS
Description:
NEW INDUSTRIAL BLDG
Architects:
- BRIGHT, RICK LANE
Contractors:
- V C I DEVELOPMENT CO INC
Permit Reviews
Permit Number - T07CM03775
Permit Status: Final
Permit Description: NEW INDUSTRIAL BLDG
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/20/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 01/20/2009 | COMPLETED |
| 02/20/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 02/25/2009 | COMPLETED |
| 02/20/2009 | 3RD PARTY REVIEW-REVISION/OTHER-2ND | 02/25/2009 | COMPLETED |
| 09/18/2007 | PLANS OK TO SUBMIT - 3RD PARTY | 09/20/2007 | COMPLETED |
| 09/20/2007 | 3RD PARTY REVIEW-COMMERCIAL | 11/21/2007 | COMPLETED |
| 11/21/2007 | POST 3RD PARTY REVIEW | 01/30/2008 | COMPLETED |
| 12/04/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 12/04/2008 | COMPLETED |
| 12/04/2008 | RESUBMITTAL | 12/08/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM03775
Permit Status: Final
Permit Description: NEW INDUSTRIAL BLDG
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/18/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T07CM03775
Permit Description: NEW INDUSTRIAL BLDG
Total Completed Inspections - 41
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/15/2008 | ELECTRIC - TEMPORARY SERVICE | CCLEMENS | Approved | IVRS - Inspection :* |
| 06/06/2008 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
| 11/07/2008 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* INFORMATION ONLY |
| 11/19/2008 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* TILT-UP PANELS @ FOOTINGS -- PERIMTER -- OK TO POUR |
| 12/01/2008 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* OK STUDS AT WALL EDGES *SOME RUNS HAVE 360 DEG. AT THIS TIME |
| 12/02/2008 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/04/2008 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* OK FOR POURBACK TO EXT. PANELS |
| 01/25/2009 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/02/2009 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 02/10/2009 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/23/2009 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* NO DROP CEILINGS SHELL ONLY |
| 02/26/2009 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* LIDS ABOVE FRONT ENTRY OK |
| 03/06/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 03/09/2009 | RIGHT OF WAY - FINAL | MOTERO | Approved | |
| 03/31/2009 | SITE - SEWER | RLEDONNE | Approved | IVRS - Inspection :* |
| 04/10/2009 | PLUMBING - ROOF DRAINS | RRICH | Approved | IVRS - Inspection :* |
| 04/10/2009 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
| 04/23/2009 | U VALUE FOR WINDOW | GDABBS | Approved | IVRS - Inspection :* |
| 05/21/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | TMPP CLEARED PER R. HOLLANDER-2ND TIME SENT TO TEP |
| 05/27/2009 | PLUMBING - PROGRESS | RLEDONNE | Approved | IVRS - Inspection :* |
| 05/27/2009 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
| 05/29/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1. OK FOR FINAL SHELL ONLY 2. PROVIDE DRAINS ON EVAP. COOLER 3. WILL CHECK ON T.I. FINAL 4. PROVIDE INSULATION SHIELDS AROUND HEATER VENTS THRU ROOF |
| 05/29/2009 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 05/29/2009 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 05/29/2009 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 05/29/2009 | ELECTRIC - OUTDOOR LIGHTING | RHOLLAND | Approved | IVRS - Inspection :* |
| 05/29/2009 | ELECTRIC - PROGRESS | RHOLLAND | Approved | IVRS - Inspection :* |
| 05/29/2009 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | IVRS - Inspection :* |
| 05/29/2009 | ELECTRIC - CABLE DROP | RHOLLAND | Approved | IVRS - Inspection :* |
| 05/29/2009 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
| 05/29/2009 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
| 05/29/2009 | ENGINEERING - FINAL | MCARREON | Approved | |
| 06/01/2009 | STEM WALL/RETAINING WALL | MHENSON | Approved | |
| 06/01/2009 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* FIRE NOT FINALED WAITING FOR TI POWER TO INSTALL MONITORS - OK PER LEERAY |
| 06/01/2009 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 06/01/2009 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 06/02/2009 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 06/02/2009 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 06/02/2009 | FIRE - FINAL | LTHOMAS | Approved | |
| 07/01/2009 | NPPO - FINAL | ACONNOR | Approved | |
| 07/01/2009 | LANDSCAPE - FINAL | ACONNOR | Approved |