Permit: T07CM03205
Permit Details
Apply Date:
08/01/2007
Applicant:
N/A
Description:
FACADE RENOVATION
Architects:
- BRIGHT, RICK LANE
Contractors:
- DIVISION II CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T07CM03205
Permit Status: Final
Permit Description: FACADE RENOVATION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/17/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 04/22/2009 | COMPLETED |
| 08/01/2007 | PLANS OK TO SUBMIT - COMM | 08/01/2007 | COMPLETED |
| 08/01/2007 | 3RD PARTY REVIEW-COMMERCIAL | 08/17/2007 | COMPLETED |
| 08/13/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 08/17/2009 | COMPLETED |
| 08/17/2007 | POST 3RD PARTY REVIEW | 09/05/2007 | COMPLETED |
| 08/25/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 08/27/2009 | COMPLETED |
| 09/05/2007 | RESUBMITTAL | 09/06/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM03205
Permit Status: Final
Permit Description: FACADE RENOVATION
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/01/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T07CM03205
Permit Description: FACADE RENOVATION
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/19/2007 | PLUMBING - GAS PRESS TEST FNL | RRICH | Approved | IVRS - Inspection :* |
| 10/19/2007 | PLUMBING - GAS PRESSURE TEST | RRICH | Approved | IVRS - Inspection :* |
| 12/13/2007 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* STEM WALL LINE 83-86 TO BE CHANGED TO MONO-POUR; AWAITING RFI FROM ARCHITECT |
| 12/19/2007 | FRAMING | JBURGE | Approved | IVRS - Inspection :* UPPER ROOF: CANOPY - LOBBY PARAPET #B3 PAGE A5.4 OK TO COVER PROGRESS AREAS |
| 12/20/2007 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* 4 @ F4 COLUMN FOOTINGS LINE B/71; 2 @ F2 COLUMN FOOTINGS ON LINE 65 -- OK TO POUR PAGE S1/4.1 |
| 12/31/2007 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* CANCELLED BY CONTRACTOR |
| 02/06/2008 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* TEMPERED GLASS SYSTEM |
| 03/13/2008 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO DRY IN ROOFING COMPLETE SECTION C/2 TO C/3 D/2 TO D/3 |
| 05/05/2008 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* COLUMNS & SOUTH PARAPET WALLS |
| 06/13/2008 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 06/13/2008 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* |
| 07/09/2008 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 07/09/2008 | FIRE - FINAL | LTHOMAS | Approved | |
| 03/11/2009 | ENGINEERING - FINAL | JBRUCKME | Approved | |
| 04/23/2009 | OUTDOOR LIGHTING FINAL | LHANLY | Approved | |
| 04/23/2009 | ELECTRIC - FINAL | LHANLY | Approved | PLAN REVISIONS APPROVED PER RED-LINES |
| 04/23/2009 | ELECTRIC - OUTDOOR LIGHTING | LHANLY | Approved | REVISIONS FOR ADDING 6 CANS APPROVED |
| 04/23/2009 | ELECTRIC - CONSTRUCTION POWER | LHANLY | Approved | |
| 04/23/2009 | ELECTRIC - ABOVE CEILING | LHANLY | Approved | |
| 04/23/2009 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | |
| 09/22/2009 | PLUMBING - ROOF DRAINS | RMYERS | Approved | IVRS - Inspection :* |
| 09/24/2009 | PLUMBING - FINAL | RMYERS | Approved | 1) INSTALL SCUPPER AND DOWNSPOUT PER PLAN |
| 10/02/2009 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* 1) ALL TRADES AND FIRE FINALS ARE COMPLETE |
| 10/05/2009 | PERMIT FINALED | JWEATHER | Approved |