Permit: T07CM02838
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
184 S AVENIDA DEL SEMBRADOR
Address NEW:
184 S AVENIDA DEL SEMBRADOR
Apply Date:
07/03/2007
Applicant:
N/A
Description:
SFR TD # 16-83-43 R1- electrical revison R2 DELETE 3 GAS APPLIANCES
Contractors:
- TUCSON ARTISAN BUILDERS L L C
Outstanding Activity Conditions
Permit Number - T07CM02838
Permit Status: Final
Permit Description: SFR TD # 16-83-43
R1- electrical revison
R2 DELETE 3 GAS APPLIANCES
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/03/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T07CM02838
Permit Description: SFR TD # 16-83-43
R1- electrical revison
R2 DELETE 3 GAS APPLIANCES
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/20/2007 | PLUMBING - SEWER HCS CONNECT | CRUIZ | Approved | IVRS - Inspection :* |
| 08/10/2007 | EXCAVATION/LAYOUT REBAR & ZON | CRUIZ | Approved | IVRS - Inspection :* |
| 08/20/2007 | STEM WALL/RETAINING WALL | DWALKER | Approved | IVRS - Inspection :* 1) STEMS ONLY |
| 09/11/2007 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | IVRS - Inspection :* 1) CONDUIT ONLY, NO MAIN FEEDERS GARAGE AND OK TO BURY 2) EXCEPT AT METER YARD WATER 3) OMIT POWDER ROOM FROM PLAN OR BUILD TO PLAN |
| 09/26/2007 | PLUMBING - PRE SLAB | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/27/2007 | BUILDING PRE-SLAB | CRUIZ | Approved | IVRS - Inspection :* |
| 10/25/2007 | REINFORCED MASONRY PRE-GROUT | CRUIZ | Approved | IVRS - Inspection :* |
| 11/20/2007 | ELECTRIC - UFER | CRUIZ | Approved | IVRS - Inspection :* |
| 12/12/2007 | PLUMBING - YARD WTR LINE/TEST | CRUIZ | Approved | IVRS - Inspection :* |
| 12/12/2007 | ROOF NAILING | CRUIZ | Approved | IVRS - Inspection :* |
| 01/24/2008 | PLUMBING - GAS PRESSURE TEST | CRUIZ | Approved | IVRS - Inspection :* |
| 01/24/2008 | FRAMING | CRUIZ | Approved | IVRS - Inspection :* |
| 01/24/2008 | MECHANICAL - INTERMEDIATE | CRUIZ | Approved | IVRS - Inspection :* |
| 01/24/2008 | PLUMBING - INTERMEDIATE | CRUIZ | Approved | IVRS - Inspection :* |
| 01/24/2008 | ELECTRIC - INTERMEDIATE | CRUIZ | Approved | IVRS - Inspection :* |
| 02/11/2008 | SHEET ROCK NAILING | CRUIZ | Approved | IVRS - Inspection :* |
| 02/11/2008 | U VALUE FOR WINDOW | CRUIZ | Approved | IVRS - Inspection :* |
| 02/14/2008 | STUCCO MESH | CRUIZ | Approved | IVRS - Inspection :* |
| 02/27/2008 | ELECTRIC - TEMPORARY SERVICE | CRUIZ | Approved | IVRS - Inspection :* |
| 02/27/2008 | ELECTRIC - CABLE DROP | CRUIZ | Approved | IVRS - Inspection :* |
| 02/28/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER C. RUIZ |
| 03/05/2008 | ASSURANCE | MCARREON | Approved | LOT GRADING APPROVED UNDER FINAL SITE PLAN FOR ENTIRE PROJECT. |
| 04/29/2008 | PLUMBING - FINAL | WLAHR | Approved | IVRS - Inspection :* |
| 04/29/2008 | PLUMBING - GAS PRESS TEST FNL | WLAHR | Approved | IVRS - Inspection :* |
| 04/30/2008 | MECHANICAL - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/30/2008 | ELECTRIC - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/30/2008 | BUILDING - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 05/01/2008 | PERMIT FINALED | BFLORES | Approved | |
| 05/01/2008 | SITE - SEWER | RCAMACHO | Approved |