Apply Date:
03/28/2007
Applicant:
U S SALES COMPANY L L C
Description:
DUPLEX:16-88-66 T07-M0025
Contractors:
- U S SALES COMPANY L L C
Permit Reviews
Permit Number - T07CM01241
Permit Status: Si_xpire
Permit Description: DUPLEX:16-88-66 T07-M0025
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/28/2007 | RESIDENTIAL BLDG-MODEL PLAN/ENGINE/WALK THRU | 03/29/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM01241
Permit Status: Si_xpire
Permit Description: DUPLEX:16-88-66 T07-M0025
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
03/28/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
03/28/2007 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Completed Inspections
Permit Status: Si_xpire
Permit Number: T07CM01241
Permit Description: DUPLEX:16-88-66 T07-M0025
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/30/2007 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* 1. OK TO COVER ABS UNDERGROUND WITH CLEAN FILL 2. SEWER OK TO COVER REDLINE UPSTREAM MANHOLE AND FINISHED FLOOR LEVER ON PLUMBING PLAN. |
08/30/2007 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* |
09/11/2007 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* |
09/11/2007 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* |
09/11/2007 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
12/04/2007 | EXT METAL CLIPS/EXT SHEATHING | CRUIZ | Approved | IVRS - Inspection : See detailed listing on site.| 999* 1) NEED TO CHECK A.B. LAYOUT-24" ON CENTER SHEARWALLS-32" ON CENTER ON EAST EXT. WALLS 2) NEED TO RETRO BHOLDOWNS ON INTERIOR SHEARWALLS 3) NEED RETRO FOR EXTERIOR WALL HOLDOWNS AT NORTH AND SOUTH END OF DUPLEX STRUCTURE 4) NEED MORE NAILS 2ND FLOOR SOLE PLATES 5) OK TO DRY ROOF IN |
12/04/2007 | ROOF NAILING | CRUIZ | Approved | IVRS - Inspection :* |
01/11/2008 | PLUMBING - YARD WTR LINE/TEST | DWALKER | Approved | IVRS - Inspection :* 1) RECEIVED A COPY OF LETTER FROM ARCHITECT ON WATER SERVICE FOR FILES. CONTRACTOR/ARCHITECT TO SUBMIT TO CITY FOR REVIEW. THIS LETTER IS FOR 508 AND 523 LEE ST & 515 E. DRACHMAN |
01/29/2008 | ELECTRIC - INTERMEDIATE | CRUIZ | Approved | IVRS - Inspection :* |
01/29/2008 | STUCCO MESH | CRUIZ | Approved | IVRS - Inspection :* |
02/05/2008 | FRAMING | DWALKER | Approved | IVRS - Inspection :* |
02/05/2008 | MECHANICAL - INTERMEDIATE | DWALKER | Approved | IVRS - Inspection :* |
02/05/2008 | PLUMBING - INTERMEDIATE | DWALKER | Approved | IVRS - Inspection :* |
02/21/2008 | SHEET ROCK NAILING | CRUIZ | Approved | IVRS - Inspection :* |
04/03/2008 | ELECTRIC - TEMPORARY SERVICE | CRUIZ | Approved | IVRS - Inspection :* |
04/03/2008 | ELECTRIC - CABLE DROP | CRUIZ | Approved | IVRS - Inspection :* |
04/04/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED FOR UNITS #1 & 2 PER C. RUIZ |
07/21/2008 | MECHANICAL - FINAL | CRUIZ | Approved | IVRS - Inspection :* |
07/21/2008 | ELECTRIC - FINAL | CRUIZ | Approved | IVRS - Inspection :* |
07/23/2008 | PLUMBING - FINAL | CRUIZ | Approved | IVRS - Inspection :* |
07/23/2008 | BUILDING - FINAL | CRUIZ | Approved | IVRS - Inspection :* |
01/16/2009 | PERMIT FINALED | LJACKSON | Approved |