Permit: T07CM00892
Permit Details
Apply Date:
03/06/2007
Applicant:
CARROLL AND ASSOCIATES , GEORGE
Description:
NEW DUPLEX TD# 16-88-62 T07-M0021
Contractors:
- CARROLL AND ASSOCIATES , GEORGE
Outstanding Activity Conditions
Permit Number - T07CM00892
Permit Status: Final
Permit Description: NEW DUPLEX TD# 16-88-62 T07-M0021
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/06/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T07CM00892
Permit Description: NEW DUPLEX TD# 16-88-62 T07-M0021
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/19/2007 | ELECTRIC - UFER | EDURAZO | Approved | IVRS - Inspection :* |
| 12/19/2007 | EXCAVATION/LAYOUT REBAR & ZON | EDURAZO | Approved | IVRS - Inspection :* |
| 12/26/2007 | REINFORCED MASONRY PRE-GROUT | WNORTH | Approved | IVRS - Inspection :* 1) STEM WALL AND BOND BEAM APPROVED |
| 12/26/2007 | STUCCO MESH | WNORTH | Approved | IVRS - Inspection :* |
| 12/26/2007 | FRAMING | WNORTH | Approved | IVRS - Inspection :* |
| 01/04/2008 | PLUMBING - ROUGH, SOIL | EDURAZO | Approved | IVRS - Inspection :* 1) EXTEND CLEANOUT AT HCS TO GRADE |
| 01/04/2008 | PLUMBING - SEWER HCS CONNECT | EDURAZO | Approved | IVRS - Inspection :* |
| 01/04/2008 | PLUMBING - YARD WTR LINE/TEST | EDURAZO | Approved | IVRS - Inspection :* |
| 01/08/2008 | PLUMBING - PRE SLAB | EDURAZO | Approved | IVRS - Inspection :* |
| 01/08/2008 | BUILDING PRE-SLAB | EDURAZO | Approved | IVRS - Inspection :* |
| 01/22/2008 | STEM WALL/RETAINING WALL | EDURAZO | Approved | IVRS - Inspection :* |
| 02/20/2008 | ROOF NAILING | WNORTH | Approved | IVRS - Inspection :* |
| 02/20/2008 | EXT METAL CLIPS/EXT SHEATHING | WNORTH | Approved | IVRS - Inspection :* |
| 05/12/2008 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 05/12/2008 | PLUMBING - GAS PRESSURE TEST | RCAMACHO | Approved | IVRS - Inspection :* |
| 05/12/2008 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 05/14/2008 | PLUMBING - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 06/02/2008 | SHEET ROCK NAILING | EDURAZO | Approved | IVRS - Inspection :* |
| 07/07/2008 | ELECTRIC - TEMPORARY SERVICE | RCAMACHO | Approved | |
| 07/07/2008 | ELECTRIC - CABLE DROP | RCAMACHO | Approved | |
| 07/08/2008 | TEP CLEARANCE - AM | BFLORES | Approved | ECO PER R.CAMACHO |
| 08/07/2008 | MECHANICAL - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 08/07/2008 | PLUMBING - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 08/07/2008 | ELECTRIC - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 08/20/2008 | BUILDING - FINAL | RCAMACHO | Approved | |
| 08/22/2008 | PERMIT FINALED | JWEATHER | Approved |