Permit: T07BU00533
Permit Details
Apply Date:
03/08/2007
Applicant:
RICHARD SARTI
Description:
GRADING:15500CY CUT 2200CY FILL
Contractors:
- EAGLE ROCK CONSTRUCTION ,
Permit Reviews
Permit Number - T07BU00533
Permit Status: Final
Permit Description: GRADING:15500CY CUT 2200CY FILL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/27/2008 | REVISION - GRADING | 02/29/2008 | COMPLETED |
03/08/2007 | PLANS OK TO SUBMIT - GRADING | 03/08/2007 | COMPLETED |
03/08/2007 | GRADING | 06/22/2007 | COMPLETED |
06/22/2007 | RESUBMITTAL - GRADING | 02/05/2008 | COMPLETED |
10/28/2009 | REVISION - GRADING | 10/30/2009 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T07BU00533
Permit Description: GRADING:15500CY CUT 2200CY FILL
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/03/2008 | GRADING - CHECK FOR ACTIVITY | JBRUCKME | Approved | NO ACTIVITY |
04/09/2008 | ENGINEERING PRE-CONSTRUCTION | JBRUCKME | Approved | PRE-CON MEETING WITH OASIS TUCSON DAVID OLLANIK 322-3900 O'LEARY CONSTRUCTION V.P. PAUL McGILL 349-3303 GRADING & PAVING BO STANDIFER 349-6889 UNDERGROUND SUPRINTENDENT RANDY HERBERT 349-1709 1. STORMWATER CONTROLS WILL BE INSTALLED AS NORTH AND EAST PERIMETERS ARE BEING GRUBBED BEGINNING APRIL 21, 2008 AND COMPLETED ON 4/22/08. 2. FOLLOW-UP PRE-CON AND INSTALL OF CONTROLS INSPECTIONS WILL BE CALLED IN BY CONTRACTOR. 3. READ AND FILL IN THE BLANKS ON THE PRE-CON AND SWPPP DOCUMENTS AND PROVIDE A COPY OF THE COMPLETED PRE-CON DOCUMENT TO THE INSPECTOR AT THE NEXT INSPECTION. 4. POST THE AZPDES AUTHORIZATION AND UPDATE THE INFORMATION TO ADEQ. 5. PROVIDE A SCHEDULE FOR THE NORTH & EAST WALL CONSTRUCTION. |
05/29/2008 | STORMWATER FOLLOW-UP INSP | JBRUCKME | Approved | 7 DAYS FOR COMPLIANCE OR NOV AND STOP WORK ORDER WILL BE ISSUED. 1. PROVIDE COMPLETE PERIMETER CONTROLS (V-DITCH). 2. EXCAVATE SEDIMENTATION BASINS. 3. PROVIDE STRAW BALE WEIR DISCHARGE POINTS ON SEDIMENTATION BASINS. 4. TRACK AND COMPACT SLOPES ON OUTSIDE PERIMETER. |
01/29/2010 | GRADING - INTERMEDIATE | MRUSSO | Approved | |
01/29/2010 | STORMWATER FINAL INSPECTION | MRUSSO | Approved | ALL GRADING ISSUES AND CONCERNS WILL BE ADDRESSED UNDER PERMIT #T07BU00352. MOST SITE WORK COMPLETED, SOME MINOR GRADING W/ INDIVIDUAL LOTS REMAIN. STORM WATER CONCERNS ARE MINIMAL, HOWEVER SITE IS NOT BUILT OUT. |
01/29/2010 | STORMWATER INSTALL OF CONTROLS | MRUSSO | Approved | |
01/29/2010 | GRADING - FINAL | MRUSSO | Approved | ALL GRADING ISSUES AND CONCERNS WILL BE ADDRESSED UNDER PERMIT #T07BU00352. MOST SITE WORK COMPLETED, SOME MINOR GRADING W/ INDIVIDUAL LOTS REMAIN. STORM WATER CONCERNS ARE MINIMAL, HOWEVER SITE IS NOT BUIT OUT. |
11/01/2011 | LANDSCAPE INSPECTION | DROBERTS | Approved | THE LANDSCAPE INSPECTION FOR THIS PERMIT WILL BE PERFORMED DURING THE FINAL LANDSCAPE INSPECTION FOR PERMIT NUMBER T07BU00352. ALL APPEARS TO BE ACCEPTABLE AT THIS TIME FOR A FULL CLOSURE OF THE SITE, ALL ITEMS WILL BE RECHECKED PRIOR TO SIGNING OFF THE FINAL INSPECTION FOR THE PREVIOUSLY NOTED PERMIT. |
11/01/2011 | NPPO PRE PERMIT INSPECTION | DROBERTS | Approved |