Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T06CM06155
Permit Details
Status:
Final
Type:
COMMERCIAL ALTERATION
Address:
3002 N CAMPBELL AV #100
Address NEW:
3002 N CAMPBELL AV #100
Apply Date:
12/04/2006
Applicant:
RAUL REYES
Description:
NEW ELEVATOR AND STAIRWAY R1: electrical revisons
Contractors:
- TOWNWEST DESIGN DEVELOPMENT INC
Permit Reviews
Permit Number - T06CM06155
Permit Status: Final
Permit Description: NEW ELEVATOR AND STAIRWAY
R1: electrical revisons
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/12/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 10/25/2007 | COMPLETED |
| 12/04/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 12/05/2006 | COMPLETED |
| 12/05/2006 | 3RD PARTY REVIEW-COMMERCIAL TI | 12/05/2006 | COMPLETED |
| 12/05/2006 | OTHER | 12/05/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM06155
Permit Status: Final
Permit Description: NEW ELEVATOR AND STAIRWAY
R1: electrical revisons
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/04/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T06CM06155
Permit Description: NEW ELEVATOR AND STAIRWAY
R1: electrical revisons
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/07/2006 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* FOUNDATION & COLUMNS FOR ELEVATOR & STAIRWELL OK TO POUR |
| 01/16/2007 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* OK TO CAP & GROUT @ 24'10" |
| 02/07/2007 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* 1) 3" RAIN DRAIN SHOWN ON A2.1 UNDERGROUND ONLY 2) WATER TEST OK 3) SHALL WRAP 90 DEGREE UP TO CONCRETE |
| 02/15/2007 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/21/2007 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/27/2007 | ELECTRIC - PROGRESS | CCLEMENS | Approved | IVRS - Inspection :* OK WALL COVER 2ND LEVEL STRIP LIGHT. |
| 03/27/2007 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
| 03/27/2007 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
| 04/03/2007 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/03/2007 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/06/2007 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 05/11/2007 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 05/11/2007 | ELECTRIC - UNDERGROUND | CCLEMENS | Approved | IVRS - Inspection :* |
| 09/11/2007 | ELECTRIC - FINAL | CCLEMENS | Approved | IVRS - Inspection :* REVISED PLAN TO BE RESUBMITTED AND APPROVED THROUGH PLAN REVIEW |
| 09/11/2007 | OUTDOOR LIGHTING FINAL | CCLEMENS | Approved | IVRS - Inspection :* |
| 09/11/2007 | ELECTRIC - OUTDOOR LIGHTING | CCLEMENS | Approved | IVRS - Inspection :* |
| 09/11/2007 | ELECTRIC - INTERMEDIATE | CCLEMENS | Approved | IVRS - Inspection :* |
| 01/24/2008 | RIGHT OF WAY - FINAL | MOTERO | Approved | PER EMAIL |
| 01/24/2008 | FIRE - FINAL | CSCHULTZ | Approved | |
| 01/24/2008 | NPPO - FINAL | ACONNOR | Approved | N/A |
| 01/24/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
| 01/25/2008 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 05/09/2008 | SIGN - FINAL | JYBARRA | Approved |