Permit: T06CM05858
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
3936 E FORT LOWELL RD #200*
Address NEW:
3936 E FORT LOWELL RD #200*
Apply Date:
11/14/2006
Applicant:
SWAN WAYNE E
Description:
TI:OFFICE Revision #1 - Delta 1 dated 2/23/07 revise drawings clarifying building is non-sprinklered
Architects:
- SWAN WAYNE E
Contractors:
- EPSTEIN FENTON L L C ,
Permit Reviews
Permit Number - T06CM05858
Permit Status: C of o
Permit Description: TI:OFFICE
Revision #1 - Delta 1 dated 2/23/07 revise drawings clarifying building is non-sprinklered
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/26/2007 | REVISION - - 1ST | 04/13/2007 | COMPLETED |
| 11/14/2006 | COMMERCIAL TI | 11/21/2006 | COMPLETED |
| 11/21/2006 | RESUBMITTAL | 01/08/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM05858
Permit Status: C of o
Permit Description: TI:OFFICE
Revision #1 - Delta 1 dated 2/23/07 revise drawings clarifying building is non-sprinklered
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/14/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM05858
Permit Description: TI:OFFICE
Revision #1 - Delta 1 dated 2/23/07 revise drawings clarifying building is non-sprinklered
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/17/2007 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 01/29/2007 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 01/29/2007 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 02/22/2007 | ELECTRIC - ABOVE CEILING | CCLEMENS | Approved | IVRS - Inspection :* |
| 03/01/2007 | ELECTRIC - FINAL | RHOLLAND | Approved | OK FINAL PER INSP. SHEET |
| 03/01/2007 | ELECTRIC - FINAL | RHOLLAND | Approved | |
| 03/01/2007 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
| 03/02/2007 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
| 03/06/2007 | FRAMING | JBURGE | Approved | IVRS - Inspection :* PHASE II COMPLETE |
| 03/09/2007 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* PHASE III - COMPLETE - OK TO TAPE |
| 03/09/2007 | PLUMBING - FINAL | BBENEDON | Approved | |
| 03/09/2007 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 03/21/2007 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* PHASE II COMPLETE |
| 03/21/2007 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
| 03/21/2007 | NPPO - FINAL | ACONNOR | Approved | N/A |
| 03/21/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
| 03/21/2007 | SIGN - FINAL | JYBARRA | Approved | |
| 03/22/2007 | FIRE - FINAL | CSCHULTZ | Approved | REPAIRS MADE |
| 03/23/2007 | ENGINEERING - FINAL | MAVERY | Approved | No work outside of building. |
| 04/13/2007 | PERMIT FINALED | LJACKSON | Approved |