Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Apply Date:
10/03/2006
Applicant:
N/A
Description:
TI:BRANCH BANK (BANK OF THE WEST)
Architects:
  • SILBERSCHLAG, WAYNE DAVID
Contractors:
  • RIO WEST DEVELOPMENT AND CONSTRU

Permit Reviews

Permit Number - T06CM05256
Permit Status: C of o
Permit Description: TI:BRANCH BANK (BANK OF THE WEST)
Start Date Submittal Complete Date Status  
03/29/2007 3RD PARTY REVIEW-REVISION/OTHER 04/09/2007 COMPLETED Review Details
10/03/2006 PLANS OK TO SUBMIT - 3RD PARTY 10/04/2006 COMPLETED Review Details
10/04/2006 3RD PARTY REVIEW-COMMERCIAL TI 11/17/2006 COMPLETED Review Details
11/17/2006 POST 3RD PARTY REVIEW 11/30/2006 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T06CM05256
Permit Status: C of o
Permit Description: TI:BRANCH BANK (BANK OF THE WEST)
Total Outstanding Activity Conditions - 1
Date Name
10/03/2006 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T06CM05256
Permit Description: TI:BRANCH BANK (BANK OF THE WEST)
Total Completed Inspections - 41
Date Description Inspector Results Comments
12/11/2006 ELECTRIC - UNDERGROUND RHOLLAND Approved IVRS - Inspection :*
OK 2 FLOOR BOXES & CONDUITS
12/12/2006 PLUMBING - ROUGH, SOIL BBENEDON Approved IVRS - Inspection :*
12/15/2006 PLUMBING - PRE SLAB BBENEDON Approved IVRS - Inspection :*
01/08/2007 BUILDING PRE-SLAB JBURGE Approved IVRS - Inspection :*
VAULT FLOOR -- OK TO POUR
01/08/2007 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved IVRS - Inspection :*
VAULT FOOTINGS OK TO POUR
01/25/2007 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
02/27/2007 FRAMING JBURGE Approved IVRS - Inspection :*
ATM AREA COMPLETE
OK TO TAPE & TEXTURE
03/25/2007 ELECTRIC - TEMP POWER FOR TEST RHOLLAND Approved IVRS - Inspection :*
03/26/2007 TEP CLEARANCE - AM JWEATHER Approved
03/26/2007 TEP CLEARANCE - AM JWEATHER Approved TMPP CLEARED FOR #1 & #2 PER R. HOLLANDER
03/30/2007 ELECTRIC - INTERMEDIATE DSANTACR Approved IVRS - Inspection :*
03/30/2007 PLUMBING - PROGRESS BBENEDON Approved IVRS - Inspection :*
03/30/2007 SITE - SEWER BBENEDON Approved IVRS - Inspection :*
03/30/2007 PLUMBING - SEWER HCS CONNECT BBENEDON Approved IVRS - Inspection :*
03/30/2007 PLUMBING - YARD WTR LINE/TEST BBENEDON Approved IVRS - Inspection :*
03/30/2007 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
03/30/2007 U VALUE FOR WINDOW JBURGE Approved IVRS - Inspection :*
03/30/2007 STUCCO MESH JBURGE Approved IVRS - Inspection :*
03/30/2007 REINFORCED MASONRY PRE-GROUT JBURGE Approved IVRS - Inspection :*
03/30/2007 STEM WALL/RETAINING WALL JBURGE Approved IVRS - Inspection :*
04/02/2007 BUILDING ABOVE CEILING JBURGE Approved
04/04/2007 MECHANICAL - UNDERGROUND JMILITEL Approved IVRS - Inspection :*
04/04/2007 ELECTRIC - UFER RHOLLAND Approved IVRS - Inspection :*
ANSWER QUESTIONS
04/04/2007 ELECTRIC - RECONNECT RHOLLAND Approved IVRS - Inspection :*
04/04/2007 ELECTRIC - SERVICE UPGRADE RHOLLAND Approved IVRS - Inspection :*
04/04/2007 ELECTRIC - PROGRESS RHOLLAND Approved IVRS - Inspection :*
04/05/2007 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
AIR BALANCE OK
OK FOR FINAL
04/05/2007 MECHANICAL - PROGRESS JMILITEL Approved IVRS - Inspection :*
04/05/2007 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
04/05/2007 NPPO - FINAL ACONNOR Approved
04/05/2007 LANDSCAPE - FINAL ACONNOR Approved
04/05/2007 RIGHT OF WAY - FINAL PWHIDDON Approved PER EMAIL
04/06/2007 PLUMBING - FINAL RRICH Approved IVRS - Inspection :*
1) ONE TIME EXCEPTION PER LETTER FROM PROFESSIONAL ENGINEERING TECHNOLOGY DATED 4/5/07
04/06/2007 ELECTRIC - FINAL RHOLLAND Approved IVRS - Inspection :*
1) OK FINAL
04/06/2007 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*
04/06/2007 BUILDING - PROGRESS JBURGE Approved IVRS - Inspection :*
04/06/2007 FIRE - FINAL LTHOMAS Approved
04/06/2007 FIRE SPKLR - FINAL LTHOMAS Approved
10/11/2007 ENGINEERING - FINAL JBRUCKME Approved
10/29/2007 PERMIT FINALED JYBARRA Approved
10/29/2007 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*

Documents

File Name Document Type  
C OF O_11-05-2007.TIF CERT OF OCC VIEW
None CERT OF OCC VIEW
None DOCUMENTS VIEW
5256-01-0001-01-REVISION001.TIF CONSTRPLANS VIEW
5256-01-0001-01-REVISION002.TIF CONSTRPLANS VIEW
5256-01-0001-01-REVISION003.TIF CONSTRPLANS VIEW
5256-01-0001-01-REVISION004.TIF CONSTRPLANS VIEW
5256-01-0001-01-REVISION005.TIF CONSTRPLANS VIEW
5256-01-0001-01-REVISION006.TIF CONSTRPLANS VIEW
5256-01-0001-01-REVISION007.TIF CONSTRPLANS VIEW
5256-01-0001-01-REVISION008.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL001.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL002.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL003.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL004.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL005.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL006.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL007.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL008.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL009.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL010.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL011.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL012.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL013.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL014.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL015.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL016.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL017.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL018.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL019.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL020.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL021.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL022.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL023.TIF CONSTRPLANS VIEW
5256-01-0001-01-ORIGINAL024.TIF CONSTRPLANS VIEW