Permit: T06CM05109
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
8526 E TANQUE VERDE RD 04
Address NEW:
8526 E TANQUE VERDE RD 04
Apply Date:
09/20/2006
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEW BARN # 4
Architects:
- COLE, BENJAMIN WILLIAM
Contractors:
- HALLMARK CUSTOM HOMES L L C
Permit Reviews
Permit Number - T06CM05109
Permit Status: C of o
Permit Description: NEW BARN # 4
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/05/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 06/06/2007 | COMPLETED |
| 06/20/2008 | 3RD PARTY REVIEW-REVISION/OTHER-2ND | 07/14/2008 | COMPLETED |
| 07/14/2008 | RESUBMITTAL | 07/16/2008 | COMPLETED |
| 09/20/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 09/20/2006 | COMPLETED |
| 09/20/2006 | 3RD PARTY REVIEW-COMMERCIAL | 11/27/2006 | COMPLETED |
| 10/20/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 10/27/2008 | COMPLETED |
| 11/27/2006 | POST 3RD PARTY REVIEW | 01/12/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM05109
Permit Status: C of o
Permit Description: NEW BARN # 4
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/20/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM05109
Permit Description: NEW BARN # 4
Total Completed Inspections - 35
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/01/2007 | STEM WALL/RETAINING WALL | JBURGE | Approved | OK TO GROUT |
| 11/27/2007 | FRAMING | JBURGE | Approved | IVRS - Inspection :* 1) STEEL STRUCTURE; OK TO SET ROOF SYSTEM |
| 12/17/2007 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* EAST & WEST GABLES TOPPED OUT; SOUTH WALL (CENTER) 12'-16'; NORTH WALL (CENTER) 8'-12' -- GROUTED SPECIAL INSPECTED |
| 07/23/2008 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | INTERIOR FOOTINGS AS PER DETAIL #108; OK TO POUR |
| 07/23/2008 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | CONTINUOUS FOOTINGS & INTERIOR COLUMNS (20) |
| 08/14/2008 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* OK TO POUR SLABS |
| 08/21/2008 | SITE - SEWER | BBENEDON | Approved | IVRS - Inspection :* |
| 08/21/2008 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
| 08/21/2008 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 08/22/2008 | ELECTRIC - UFER | RJIROUDE | Approved | IVRS - Inspection :* OK GROUNDING GRID |
| 08/22/2008 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* |
| 10/28/2008 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* 1. OK HARD LIDS. EXCEPT PORCH AREAS. 2. OK PANEL & XFMR -- OK TO ENERGIZE WHEN READY |
| 10/28/2008 | ELECTRIC - TEMP POWER FOR TEST | RJIROUDE | Approved | IVRS - Inspection :* |
| 11/05/2008 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* CONN. TO BUILDING OK |
| 11/18/2008 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* METAL ROOF SYSTEM IN PLACE |
| 11/18/2008 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 11/20/2008 | PLUMBING - GAS PRESSURE TEST | RLEDONNE | Approved | IVRS - Inspection :* FROM METER TO WEST SIDE OF BUILDING UNDERGROUND GAS PIPING TEST OK (ONLY) |
| 12/31/2008 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 1) TACK ROOMS (2), WASHROOM, TACK LOCKERS-CEILINGS OK TO TAPE PROGRESS AREAS |
| 12/31/2008 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 01/05/2009 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 01/09/2009 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 01/09/2009 | PLUMBING - GAS PRESS TEST FNL | RLEDONNE | Approved | IVRS - Inspection :* |
| 01/09/2009 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
| 01/13/2009 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* BARN #4 LIGHTING AND ELECTRIC FINAL OK |
| 01/13/2009 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | IVRS - Inspection :* |
| 01/13/2009 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
| 01/13/2009 | OUTDOOR LIGHTING FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 01/16/2009 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 01/16/2009 | FIRE - FINAL | LTHOMAS | Approved | |
| 01/21/2009 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
| 01/28/2009 | ENGINEERING - FINAL | JBRUCKME | Approved | |
| 01/28/2009 | SIGN - FINAL | JYBARRA | Approved | |
| 01/29/2009 | NPPO - FINAL | ACONNOR | Approved | |
| 01/29/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 01/29/2009 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |