Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T06CM03162
Permit Details
Apply Date:
05/26/2006
Applicant:
N/A
Description:
TH: TD#16-65-36
Contractors:
- LOUIS MARSON AND SONS INC
Permit Reviews
Permit Number - T06CM03162
Permit Status: Final
Permit Description: TH: TD#16-65-36
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/26/2006 | RESIDENTIAL BLDG-MODEL PLAN/ENGINE/WALK THRU | 05/26/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM03162
Permit Status: Final
Permit Description: TH: TD#16-65-36
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
05/26/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T06CM03162
Permit Description: TH: TD#16-65-36
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/07/2006 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* 1. ABS DWV "DUAL" ROUGH INSTALLED OK. WATER TEST RISER TO TEN FEET 2. OK TO BACKFILL |
06/16/2006 | BUILDING PRE-SLAB | AALEGRIA | Approved | IVRS - Inspection :* |
06/16/2006 | EXCAVATION/LAYOUT REBAR & ZON | AALEGRIA | Approved | IVRS - Inspection :* |
06/21/2006 | ELECTRIC - UFER | CCLEMENS | Approved | IVRS - Inspection :* |
10/11/2006 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection :* OK TO DRY IN CHECK DRAG TRUSS BRACING. |
10/23/2006 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection :* |
12/19/2006 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
12/26/2006 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* 1. ALL BLDGS REQUIRED TO HAVE ADDRESSES POSTED! 2. OK TO COVER ALL AREAS |
01/23/2007 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | OK FOR SHEETROCK |
01/25/2007 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
01/31/2007 | ELECTRIC - INTERMEDIATE | CCLEMENS | Approved | IVRS - Inspection :* |
02/21/2007 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
04/11/2007 | STUCCO MESH | LHANLY | Approved | IVRS - Inspection :* |
05/10/2007 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
05/14/2007 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
06/04/2007 | ELECTRIC - TEMPORARY SERVICE | RMAJUTA | Approved | IVRS - Inspection :* |
06/05/2007 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER R. MAJUTA |
06/18/2007 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* SHOWER PAN LINERS OK |
09/20/2007 | PLUMBING - ABOVE CEILING | RMYERS | Approved | |
09/20/2007 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | |
09/20/2007 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | |
09/20/2007 | OUTDOOR LIGHTING FINAL | CCLEMENS | Approved | |
09/20/2007 | ELECTRIC - PROGRESS | CCLEMENS | Approved | |
09/20/2007 | ELECTRIC - ABOVE CEILING | CCLEMENS | Approved | |
09/20/2007 | ELECTRIC - CABLE DROP | CCLEMENS | Approved | |
09/20/2007 | ELECTRIC - OUTDOOR LIGHTING | CCLEMENS | Approved | |
09/20/2007 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* 1) PLUMBING FINAL OK 2) OK FOR C OF O S.T.O.I. |
09/20/2007 | ELECTRIC - FINAL | CCLEMENS | Approved | IVRS - Inspection :* |
09/27/2007 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* AC-2 CONTROL VOLTAGE CONDUIT NOT PROPERLY SEALED AT ROOF |
09/27/2007 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | |
09/28/2007 | BUILDING ABOVE CEILING | AQUIROZ | Approved | |
09/28/2007 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
09/28/2007 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
09/28/2007 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection :* |
03/25/2008 | PERMIT FINALED | LJACKSON | Approved |