Permit: T06CM02733
Permit Details
Status:
Final
Type:
COMMERCIAL ALTERATION
Address:
4125 E SPEEDWAY BL #101
Address NEW:
4125 E SPEEDWAY BL #101
Apply Date:
05/09/2006
Applicant:
WILLIAM STAMM
Description:
ADDITION: 3 BATHROOMS AND AIR CONDITIONING
Contractors:
- SILVER WEST INC ,
Permit Reviews
Permit Number - T06CM02733
Permit Status: Final
Permit Description: ADDITION: 3 BATHROOMS AND AIR CONDITIONING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/09/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 05/09/2006 | COMPLETED |
| 05/09/2006 | 3RD PARTY REVIEW-COMMERCIAL TI | 06/02/2006 | COMPLETED |
| 06/02/2006 | POST 3RD PARTY REVIEW | 06/15/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM02733
Permit Status: Final
Permit Description: ADDITION: 3 BATHROOMS AND AIR CONDITIONING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/09/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T06CM02733
Permit Description: ADDITION: 3 BATHROOMS AND AIR CONDITIONING
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/10/2006 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 07/12/2006 | SITE - SEWER | RLEDONNE | Approved | IVRS - Inspection :* |
| 07/12/2006 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | IVRS - Inspection :* |
| 07/12/2006 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
| 07/12/2006 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
| 07/24/2006 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* 1. SUPPORT VDV CABELING CORRECTLY, TAPE TO PIPES NOT ALLOWED. 2. SUPPORT FIXTURES TO GRID. 2 SCREWS ON CENTER OR 4 ON CORNERS SUPPORT FROM STRUCTURE AND M/C TO BE SUPPORTED AS PER 300.11 OK WALLS AND HARD LIDS. |
| 07/27/2006 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO TAPE |
| 08/16/2006 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* OK FOR CEILING TILES |
| 08/16/2006 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* BUILDING ABOVE CEILING |
| 08/16/2006 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 08/17/2006 | ELECTRIC - ABOVE CEILING | RMAJUTA | Approved | IVRS - Inspection :* |
| 08/17/2006 | ELECTRIC - INTERMEDIATE | RMAJUTA | Approved | IVRS - Inspection :* |
| 09/01/2006 | ENGINEERING - FINAL | JBRUCKME | Approved | |
| 09/01/2006 | ELECTRIC - SERVICE UPGRADE | RHOLLAND | Approved | IVRS - Inspection :* |
| 09/01/2006 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | IVRS - Inspection :* |
| 09/01/2006 | ELECTRIC - CONSTRUCTION POWER | RHOLLAND | Approved | IVRS - Inspection :* |
| 09/01/2006 | FIRE - FINAL | LTHOMAS | Approved | |
| 09/01/2006 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
| 09/01/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 09/05/2006 | TEP CLEARANCE - AM | BFLORES | Approved | TMPP PER R.HOLLANDER ("A", "B", "C") |
| 09/22/2006 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 09/22/2006 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 10/02/2006 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 10/16/2006 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* OK FOR FINAL AIR BALANCE REPORT MEETS REQUIRED QUANTITIES. |
| 10/16/2006 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 10/17/2006 | PERMIT FINALED | BFLORES | Approved | |
| 10/17/2006 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved |