Permit: T06CM01834
Permit Details
Apply Date:
03/31/2006
Applicant:
JOE BANKS
Description:
SFR:NEW
Contractors:
- KACHINA GENERAL CONTRACTORS L L C
Permit Reviews
Permit Number - T06CM01834
Permit Status: Final
Permit Description: SFR:NEW
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/31/2006 | PLANS OK TO SUBMIT - RES | 04/03/2006 | COMPLETED |
04/03/2006 | 3RD PARTY REVIEW-RESIDENTIAL | 04/27/2006 | COMPLETED |
04/24/2007 | POST 3RD PARTY REVIEW | 05/15/2007 | COMPLETED |
05/31/2006 | POST 3RD PARTY REVIEW | 08/11/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM01834
Permit Status: Final
Permit Description: SFR:NEW
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/31/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T06CM01834
Permit Description: SFR:NEW
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/18/2006 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | IVRS - Inspection :* |
08/24/2006 | PLUMBING - PRE SLAB | RCAMACHO | Approved | IVRS - Inspection :* |
08/24/2006 | ELECTRIC - UFER | RCAMACHO | Approved | IVRS - Inspection :* |
08/29/2006 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | IVRS - Inspection :* |
08/29/2006 | BUILDING PRE-SLAB | RCAMACHO | Approved | IVRS - Inspection :* |
10/17/2006 | ROOF NAILING | RCAMACHO | Approved | IVRS - Inspection :* |
10/18/2006 | EXT METAL CLIPS/EXT SHEATHING | RCAMACHO | Approved | IVRS - Inspection :* 1) EXCEPT BREEZE WAY |
11/02/2006 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* 1) EXCEPT HOME RUNS TO PANEL/GAS BOND |
11/02/2006 | STUCCO MESH | RCAMACHO | Approved | IVRS - Inspection :* |
11/02/2006 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
11/02/2006 | PLUMBING - GAS PRESSURE TEST | RCAMACHO | Approved | IVRS - Inspection :* |
11/02/2006 | PLUMBING - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
11/02/2006 | FRAMING | RCAMACHO | Approved | IVRS - Inspection :* |
11/07/2006 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
12/09/2008 | PLUMBING - SEWER HCS CONNECT | DWALKER | Approved | IVRS - Inspection :* |
12/09/2008 | PLUMBING - YARD WTR LINE/TEST | DWALKER | Approved | IVRS - Inspection :* |
12/09/2008 | PLUMBING - FINAL | IVR USER | Approved | IVRS - RI canceled |
04/27/2009 | ELECTRIC - TEMPORARY SERVICE | DWALKER | Approved | IVRS - Inspection :* |
04/27/2009 | ELECTRIC - CABLE DROP | DWALKER | Approved | IVRS - Inspection :* |
04/28/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED FOR #2 PER D. WALKER |
05/15/2009 | MECHANICAL - FINAL | DWALKER | Approved | IVRS - Inspection :* |
05/19/2009 | U VALUE FOR WINDOW | DWALKER | Approved | |
05/19/2009 | BUILDING - FINAL | DWALKER | Approved | IVRS - Inspection :* |
05/19/2009 | ELECTRIC - FINAL | DWALKER | Approved | IVRS - Inspection :* |
05/20/2009 | PERMIT FINALED | JWEATHER | Approved |