Permit: T06CM01733
Permit Details
Apply Date:
03/28/2006
Applicant:
OUTPOST DEVELOPMENT
Description:
SFR: TD# 16-36-90
Contractors:
- OUTPOST DEVELOPMENT
Permit Reviews
Permit Number - T06CM01733
Permit Status: Final
Permit Description: SFR: TD# 16-36-90
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/28/2006 | RESIDENTIAL BLDG-MODEL PLAN/ENGINE/WALK THRU | 05/18/2006 | COMPLETED |
| 04/11/2007 | REVISION - - 1ST | 04/11/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM01733
Permit Status: Final
Permit Description: SFR: TD# 16-36-90
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/28/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T06CM01733
Permit Description: SFR: TD# 16-36-90
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/21/2006 | PLUMBING - ROUGH, SOIL | WNORTH | Approved | IVRS - Inspection :* |
| 08/08/2006 | EXCAVATION/LAYOUT REBAR & ZON | WNORTH | Approved | IVRS - Inspection :* 1) NO SOUTH PROCH ON PLOT PLAN 2) ELECTRIC UFER NOT INSTALLED |
| 08/08/2006 | BUILDING PRE-SLAB | WNORTH | Approved | IVRS - Inspection :* |
| 08/09/2006 | ELECTRIC - UFER | WNORTH | Approved | IVRS - Inspection :* |
| 09/15/2006 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | IVRS - Inspection :* 1) #2 BELOW NOT DONE |
| 09/15/2006 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 09/29/2006 | ELECTRIC - TEMPORARY SERVICE | WNORTH | Approved | IVRS - Inspection :* |
| 09/29/2006 | ELECTRIC - CABLE DROP | WNORTH | Approved | IVRS - Inspection :* |
| 10/02/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER W. NORTH |
| 10/26/2006 | MECHANICAL - INTERMEDIATE | WNORTH | Approved | IVRS - Inspection :* |
| 10/26/2006 | PLUMBING - GAS PRESSURE TEST | WNORTH | Approved | IVRS - Inspection :* |
| 10/26/2006 | PLUMBING - INTERMEDIATE | WNORTH | Approved | IVRS - Inspection :* |
| 10/26/2006 | U VALUE FOR WINDOW | WNORTH | Approved | IVRS - Inspection :* |
| 10/26/2006 | STUCCO MESH | WNORTH | Approved | IVRS - Inspection :* |
| 11/14/2006 | SHEET ROCK NAILING | WNORTH | Approved | IVRS - Inspection :* |
| 11/14/2006 | ELECTRIC - INTERMEDIATE | WNORTH | Approved | IVRS - Inspection :* |
| 11/14/2006 | FRAMING | WNORTH | Approved | IVRS - Inspection :* |
| 12/07/2006 | PLUMBING - SEWER HCS CONNECT | WNORTH | Approved | IVRS - Inspection :* SOMEONE NEEDS TO COORDINATE THESE INSPECTIONS FOUR WERE CALLED IN: 1 WAS READY 1 WAS DONE YESTERDAY 2 - NO CONSTRUCTION STARTED ON THOSE LOTS |
| 12/07/2006 | PLUMBING - YARD WTR LINE/TEST | WNORTH | Approved | IVRS - Inspection :* |
| 06/13/2007 | PLUMBING - FINAL | WNORTH | Approved | IVRS - Inspection :* |
| 06/18/2007 | MECHANICAL - FINAL | WNORTH | Approved | IVRS - Inspection :* |
| 06/19/2007 | ELECTRIC - FINAL | WNORTH | Approved | IVRS - Inspection :* |
| 06/19/2007 | BUILDING - FINAL | WNORTH | Approved | IVRS - Inspection :* |
| 06/20/2007 | PERMIT FINALED | BFLORES | Approved | |
| 06/20/2007 | PLUMBING - GAS PRESS TEST FNL | WNORTH | Approved |