Permit: T06CM01564
Permit Details
Apply Date:
03/21/2006
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEW STORAGE BLDG 3 (BLDG 6 ON PLANS)
Contractors:
- BOCK COMMERCIAL CONSTRUCTION L L C
Permit Reviews
Permit Number - T06CM01564
Permit Status: C of o
Permit Description: NEW STORAGE BLDG 3 (BLDG 6 ON PLANS)
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/21/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 03/27/2006 | COMPLETED |
03/27/2006 | 3RD PARTY REVIEW-COMMERCIAL | 05/22/2006 | COMPLETED |
05/22/2006 | POST 3RD PARTY REVIEW | 06/20/2006 | COMPLETED |
06/20/2006 | RESUBMITTAL | 07/26/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM01564
Permit Status: C of o
Permit Description: NEW STORAGE BLDG 3 (BLDG 6 ON PLANS)
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/21/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM01564
Permit Description: NEW STORAGE BLDG 3 (BLDG 6 ON PLANS)
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/12/2006 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* 1ST SLAB FROM WEST |
09/28/2006 | REINFORCED MASONRY PRE-GROUT | GDABBS | Approved | IVRS - Inspection :* SOUTH SITE WALL TO CELL TOWER WEST BLDG. WALL TOP OUT. |
11/13/2006 | STEM WALL/RETAINING WALL | GDABBS | Approved | IVRS - Inspection :* TWO TRASH ENCLOSURES AT SOUTH END. |
11/13/2006 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* TWO TRASH ENCLOSURES AT SOUTH END. |
12/13/2006 | ELECTRIC - UNDERGROUND | RMAJUTA | Approved | IVRS - Inspection :* |
03/29/2007 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
03/29/2007 | BUILDING - PROGRESS | GDABBS | Approved | IVRS - Inspection :* |
03/29/2007 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
03/29/2007 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
03/30/2007 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
03/30/2007 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
03/30/2007 | NPPO - FINAL | ACONNOR | Approved | |
03/30/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | |
03/30/2007 | SHEET ROCK NAILING | GDABBS | Approved | |
04/04/2007 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
04/04/2007 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
04/04/2007 | ENGINEERING - FINAL | NKALAHAR | Approved | SEE T06CM01562 |
04/04/2007 | FIRE - FINAL | LTHOMAS | Approved | |
04/06/2007 | PLUMBING - INTERMEDIATE | RJIROUDE | Approved | |
04/06/2007 | PLUMBING - YARD WTR LINE/TEST | RJIROUDE | Approved | |
04/06/2007 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | |
04/06/2007 | SIGN - FINAL | JSONKIN | Approved | IVRS - Inspection :* |
04/12/2007 | RIGHT OF WAY - FINAL | SDAMRON | Approved | PER EMAIL |