Permit: T05CM06354
Permit Details
Apply Date:
12/21/2005
Applicant:
N/A
Description:
SFR:NEW
Contractors:
- ARVAYO GENERAL CONTRACTOR INC
Permit Reviews
Permit Number - T05CM06354
Permit Status: C of o
Permit Description: SFR:NEW
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/06/2006 | RESIDENTIAL BLDG/WWM | 02/02/2006 | COMPLETED |
| 02/13/2006 | RESUBMITTAL | 02/21/2006 | COMPLETED |
| 02/21/2006 | RESUBMITTAL | 11/02/2006 | COMPLETED |
| 12/21/2005 | PLANS OK TO SUBMIT - RES 3RD PARTY | 01/06/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM06354
Permit Status: C of o
Permit Description: SFR:NEW
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/21/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM06354
Permit Description: SFR:NEW
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/28/2006 | SITE - SEWER | FVALENCI | Approved | IVRS - Inspection :* |
| 04/28/2006 | PLUMBING - ROUGH, SOIL | FVALENCI | Approved | IVRS - Inspection :* |
| 05/01/2006 | ELECTRIC - UNDERGROUND | FVALENCI | Approved | IVRS - Inspection :* |
| 05/01/2006 | ELECTRIC - UFER | FVALENCI | Approved | IVRS - Inspection :* |
| 05/01/2006 | BUILDING PRE-SLAB | FVALENCI | Approved | IVRS - Inspection :* |
| 05/01/2006 | EXCAVATION/LAYOUT REBAR & ZON | FVALENCI | Approved | IVRS - Inspection :* |
| 05/17/2006 | ROOF NAILING | EDURAZO | Approved | IVRS - Inspection :* |
| 05/17/2006 | EXT METAL CLIPS/EXT SHEATHING | EDURAZO | Approved | IVRS - Inspection :* |
| 06/22/2006 | MECHANICAL - INTERMEDIATE | CTREVILL | Approved | IVRS - Inspection :* |
| 06/22/2006 | PLUMBING - GAS PRESSURE TEST | CTREVILL | Approved | IVRS - Inspection :* |
| 06/22/2006 | ELECTRIC - INTERMEDIATE | CTREVILL | Approved | IVRS - Inspection :* |
| 06/22/2006 | U VALUE FOR WINDOW | CTREVILL | Approved | IVRS - Inspection :* |
| 06/23/2006 | PLUMBING - INTERMEDIATE | HLEYVA | Approved | |
| 06/23/2006 | STUCCO MESH | HLEYVA | Approved | |
| 06/23/2006 | FRAMING | HLEYVA | Approved | |
| 06/27/2006 | SHEET ROCK NAILING | EDURAZO | Approved | IVRS - Inspection :* |
| 07/11/2006 | ELECTRIC - CONSTRUCTION POWER | EDURAZO | Approved | IVRS - Inspection :* |
| 07/12/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED FOR UNIT #1 PER E. DURAZO |
| 12/29/2006 | MECHANICAL - FINAL | CTREVILL | Approved | IVRS - Inspection :* |
| 12/29/2006 | PLUMBING - FINAL | CTREVILL | Approved | IVRS - Inspection :* |
| 12/29/2006 | ELECTRIC - FINAL | CTREVILL | Approved | IVRS - Inspection :* |
| 12/29/2006 | BUILDING - FINAL | CTREVILL | Approved | IVRS - Inspection :* |
| 01/05/2007 | PERMIT FINALED | JWEATHER | Approved |