Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T05CM05910
Permit Details
Apply Date:
11/29/2005
Applicant:
N/A
Description:
TI: MEDICAL OFFICE
Contractors:
- BOCK BUILDING CONTRACTORS INC ,
Permit Reviews
Permit Number - T05CM05910
Permit Status: C of o
Permit Description: TI: MEDICAL OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/03/2006 | RESUBMITTAL | 01/09/2006 | COMPLETED |
04/19/2006 | REVISION - WALK THRU | 04/20/2006 | COMPLETED |
05/01/2006 | REVISION - - 1ST | 05/01/2006 | COMPLETED |
11/29/2005 | PLANS OK TO SUBMIT - COMM | 11/30/2005 | COMPLETED |
11/30/2005 | COMMERCIAL TI | 12/06/2005 | COMPLETED |
12/06/2005 | COMMERCIAL TI | 01/03/2006 | COMPLETED |
12/06/2005 | RESUBMITTAL | 04/25/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM05910
Permit Status: C of o
Permit Description: TI: MEDICAL OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/29/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM05910
Permit Description: TI: MEDICAL OFFICE
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/07/2006 | EXCAVATION/LAYOUT REBAR & ZON | JCAGLE | Approved | IVRS - Inspection :* N/A FOR THIS PROJECT |
03/28/2006 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
03/28/2006 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
03/28/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
03/29/2006 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
04/07/2006 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* OK WALL |
04/27/2006 | ELECTRIC - ABOVE CEILING | RSUBA | Approved | IVRS - Inspection :* |
04/27/2006 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
04/28/2006 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
05/03/2006 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* OK FOR CEILING TILES. |
05/03/2006 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* CLOSET FLANGES NOT FASTENED TO FLOOR. |
05/17/2006 | ELECTRIC - TEMP POWER FOR TEST | RMAJUTA | Approved | IVRS - Inspection :* 1) RED TROTTER DS ? ELECTRIC TO RC TIGHTEN GR LUG ON 2" BUSHING IN PANEL ? 2) FOR FINAL VERIFY GAS BOND AT GAS METER RE-ATTACHED |
05/18/2006 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* CLOSET FLANGES OK BE SURE TO USE THE CORRECT CLEANOUT PLUGS. |
05/18/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER R. MAJUTA |
05/24/2006 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* OK FOR FINAL LEFT GAS CARD |
05/24/2006 | ENGINEERING - FINAL | JBRUCKME | Approved | |
05/24/2006 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
05/24/2006 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | IVRS - Inspection :* |
05/24/2006 | FIRE - FINAL | LTHOMAS | Approved | |
05/24/2006 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
05/26/2006 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
05/26/2006 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |