Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T05CM05345
Permit Details
Apply Date:
10/20/2005
Applicant:
NICHOLAS MICHAEL T & KRISS L JT/RS
Description:
ADDITION: MASTER BED RM, BATH, DEN AND LAUNDRY RM
Permit Reviews
Permit Number - T05CM05345
Permit Status: Final
Permit Description: ADDITION: MASTER BED RM, BATH, DEN AND LAUNDRY RM
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/30/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 04/03/2007 | COMPLETED |
10/20/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 10/21/2005 | COMPLETED |
10/20/2005 | 3RD PARTY REVIEW-RESIDENTIAL | 11/16/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM05345
Permit Status: Final
Permit Description: ADDITION: MASTER BED RM, BATH, DEN AND LAUNDRY RM
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/20/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T05CM05345
Permit Description: ADDITION: MASTER BED RM, BATH, DEN AND LAUNDRY RM
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/23/2005 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | IVRS - Inspection :* |
12/13/2005 | STEM WALL/RETAINING WALL | FVALENCI | Approved | IVRS - Inspection :* |
01/17/2006 | PLUMBING - ROUGH, SOIL | FVALENCI | Approved | IVRS - Inspection :* |
02/23/2006 | MECHANICAL - UNDERGROUND | HLEYVA | Approved | |
02/28/2006 | BUILDING PRE-SLAB | FVALENCI | Approved | IVRS - Inspection :* |
04/11/2006 | REINFORCED MASONRY PRE-GROUT | FVALENCI | Approved | IVRS - Inspection :* |
07/27/2006 | ROOF NAILING | CTREVILL | Approved | IVRS - Inspection :* |
07/27/2006 | EXT METAL CLIPS/EXT SHEATHING | CTREVILL | Approved | IVRS - Inspection :* |
03/26/2007 | PLUMBING - GAS PRESSURE TEST | EDURAZO | Approved | IVRS - Inspection :* |
03/26/2007 | PLUMBING - INTERMEDIATE | EDURAZO | Approved | IVRS - Inspection :* |
03/26/2007 | PLUMBING - GAS PRESSURE TEST | EDURAZO | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
03/26/2007 | PLUMBING - INTERMEDIATE | EDURAZO | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
04/04/2007 | MECHANICAL - INTERMEDIATE | CTREVILL | Approved | IVRS - Inspection :* |
04/04/2007 | ELECTRIC - INTERMEDIATE | CTREVILL | Approved | IVRS - Inspection :* |
04/06/2007 | FRAMING | CTREVILL | Approved | IVRS - Inspection :* |
07/10/2007 | SHEET ROCK NAILING | DWALKER | Approved | IVRS - Inspection :* |
07/10/2007 | U VALUE FOR WINDOW | DWALKER | Approved | IVRS - Inspection :* |
06/25/2012 | STUCCO MESH | RMORENO | Approved | |
06/25/2012 | MECHANICAL - FINAL | RMORENO | Approved | IVRS - Inspection :* |
06/25/2012 | PLUMBING - FINAL | RMORENO | Approved | IVRS - Inspection :* |
06/25/2012 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
06/25/2012 | BUILDING - FINAL | RMORENO | Approved | IVRS - Inspection :* |