Permit: T05CM04994
Permit Details
Apply Date:
09/30/2005
Applicant:
N/A
Description:
EXPANSION OF BANK
Contractors:
- D K REALTEC INC ,
Permit Reviews
Permit Number - T05CM04994
Permit Status: Final
Permit Description: EXPANSION OF BANK
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/30/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 10/04/2005 | COMPLETED |
10/04/2005 | 3RD PARTY REVIEW-COMMERCIAL TI | 10/27/2005 | COMPLETED |
10/27/2005 | POST 3RD PARTY REVIEW | 11/02/2005 | COMPLETED |
11/22/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 12/05/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM04994
Permit Status: Final
Permit Description: EXPANSION OF BANK
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/30/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T05CM04994
Permit Description: EXPANSION OF BANK
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/30/2006 | FRAMING | JCAGLE | Approved | IVRS - Inspection :* ROOM #103 & SOUTH WALL @ ROOM #102 |
01/30/2006 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* |
02/17/2006 | ELECTRIC - ABOVE CEILING | RSUBA | Approved | IVRS - Inspection :* AS NOTED (WILL CHECK AT FINAL INSTALL PROPER CONDUIT SUPPORT AT 1 1/4" E.M.T. (SECURE WITHIN 3' OF J-BOX & EVERY 10' THERE AFTER. ANY QUESTIONS 954-0161 |
02/17/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
02/17/2006 | FIRE - FINAL | LTHOMAS | Approved | |
02/17/2006 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
02/17/2006 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection :* |
02/17/2006 | BUILDING ABOVE CEILING | LHANLY | Approved | IVRS - Inspection :* |
02/17/2006 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | IVRS - Inspection :* |
02/17/2006 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection :* |
02/17/2006 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* |
02/17/2006 | ENGINEERING - FINAL | NKALAHAR | Approved | NO SITE WORK |
02/23/2006 | ELECTRIC - FINAL | RSUBA | Approved | IVRS - Inspection :* |
02/24/2006 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
02/24/2006 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection :* |
03/28/2006 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* CONTRACTOR EXPOSED FLOOR CLEANOUT. SHALL BE BROUGHT UP TO FLUSH FINISH FOR FINAL. |
03/28/2006 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
03/29/2006 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
03/29/2006 | BUILDING - FINAL | RRICH | Approved | IVRS - Inspection :* |
03/31/2006 | ELECTRIC - UNDERGROUND | RSUBA | Approved | |
03/31/2006 | PLUMBING - ROUGH, SOIL | RRICH | Approved | |
09/28/2006 | PERMIT FINALED | LJACKSON | Approved |