Permit: T05CM04496
Permit Details
Apply Date:
08/29/2005
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEW OFFICE BLDG
Contractors:
- VENTURE WEST INC
Permit Reviews
Permit Number - T05CM04496
Permit Status: C of o
Permit Description: NEW OFFICE BLDG
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/18/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 01/23/2006 | COMPLETED |
08/29/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 08/31/2005 | COMPLETED |
08/31/2005 | 3RD PARTY REVIEW-COMMERCIAL | 09/26/2005 | COMPLETED |
09/26/2005 | POST 3RD PARTY REVIEW | 10/12/2005 | COMPLETED |
11/04/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 11/07/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM04496
Permit Status: C of o
Permit Description: NEW OFFICE BLDG
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/29/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM04496
Permit Description: NEW OFFICE BLDG
Total Completed Inspections - 42
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/06/2005 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :*OK PVC U.G BELOW SLAB & OUTSIDE BLD. TO SES FOR PANEL EC. & COMM CONDUIT. |
12/08/2005 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | IVRS - Inspection :* 1) SOIL WATER TEST IS OK 2) HCS CONNECTION IS OK 3) OK TO BACKFILL TRENCH |
12/13/2005 | REINFORCED MASONRY PRE-GROUT | JCAGLE | Approved | IVRS - Inspection :* |
12/14/2005 | STEM WALL/RETAINING WALL | JCAGLE | Approved | IVRS - Inspection :* |
12/20/2005 | ELECTRIC - UFER | RSUBA | Approved | IVRS - Inspection :*APPROVED |
12/21/2005 | BUILDING PRE-SLAB | JCAGLE | Approved | IVRS - Inspection :* |
12/21/2005 | EXCAVATION/LAYOUT REBAR & ZON | JCAGLE | Approved | IVRS - Inspection :* |
02/13/2006 | ROOF NAILING | JCAGLE | Approved | IVRS - Inspection :* |
03/17/2006 | STUCCO MESH | JCAGLE | Approved | IVRS - Inspection :* |
03/17/2006 | FRAMING | JCAGLE | Approved | IVRS - Inspection :* |
03/17/2006 | EXT METAL CLIPS/EXT SHEATHING | JCAGLE | Approved | IVRS - Inspection :* |
03/28/2006 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* WATER TEST WASTE & VENT THRU ROOF OK WATER PIPING WATER TEST OK CLOSET FLANGES OK |
04/04/2006 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
04/04/2006 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
04/27/2006 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* RECESSED CANS COMPLETED |
04/27/2006 | ELECTRIC - PROGRESS | RSUBA | Approved | IVRS - Inspection :* |
04/28/2006 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
04/28/2006 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* SUSPENDED ROUGH DUCT, SUPPLY & EXHAUST IN RESTROOMS. |
05/10/2006 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* PROVIDE DUCT SMOKE DETECTORS WITH AN AUDIBLE & VISIBLE ALARM IN A SUPERVISED LOCATION. WILL CHECK ON FINAL. OK FOR CEILING TILES. LEAVE OUT UNDER EACH DUCT DETECTOR. |
05/10/2006 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* TRINI JR. APP 12/8/05 |
05/10/2006 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
05/10/2006 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
05/10/2006 | ELECTRIC - CABLE DROP | RHOLLAND | Approved | IVRS - Inspection :* |
05/10/2006 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
05/11/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | CEC CLEARED FOR R. HOLLANDER |
05/18/2006 | OUTDOOR LIGHTING FINAL | RSUBA | Approved | IVRS - Inspection :* |
05/18/2006 | ELECTRIC - FINAL | RSUBA | Approved | IVRS - Inspection :* |
05/18/2006 | ELECTRIC - OUTDOOR LIGHTING | RSUBA | Approved | IVRS - Inspection :* |
05/18/2006 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* |
05/18/2006 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
05/18/2006 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
05/18/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
05/18/2006 | FIRE - FINAL | LLAKEY | Approved | |
05/18/2006 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
05/19/2006 | MECHANICAL - FINAL | JMILITEL | Approved | OK FOR FINAL |
05/19/2006 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
05/19/2006 | BUILDING - FINAL | JBURGE | Approved | |
05/22/2006 | TEP CLEARANCE - PM | JWEATHER | Approved | TMPP CLEARED PER R. HOLLANDER |
08/03/2006 | ENGINEERING - FINAL | JBRUCKME | Approved | |
08/09/2006 | NPPO - FINAL | ACONNOR | Approved | |
08/09/2006 | LANDSCAPE - FINAL | ACONNOR | Approved | |
08/14/2006 | PERMIT FINALED | DROBEY | Approved |