Permit: T05CM04401
Permit Details
Apply Date:
08/23/2005
Applicant:
STEVEN MILLER
Description:
NEW BANK
Permit Reviews
Permit Number - T05CM04401
Permit Status: Withdrwn
Permit Description: NEW BANK
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/06/2006 | RESUBMITTAL | 07/21/2006 | COMPLETED |
| 06/06/2006 | SITE | 07/21/2006 | COMPLETED |
| 06/16/2006 | RESUBMITTAL | 09/01/2006 | ACTIVE |
| 07/21/2006 | RESUBMITTAL - SITE ALL | 09/25/2006 | COMPLETED |
| 08/15/2006 | OTHER | 08/15/2006 | COMPLETED |
| 08/23/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 08/26/2005 | COMPLETED |
| 08/23/2005 | PLANS OK TO SUBMIT - SITE | 08/26/2005 | COMPLETED |
| 08/26/2005 | COMMERCIAL NEW | 10/04/2005 | COMPLETED |
| 10/20/2005 | COMMERCIAL NEW | 06/06/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM04401
Permit Status: Withdrwn
Permit Description: NEW BANK
Total Outstanding Activity Conditions - 10
| Date | Name |
|---|---|
| 08/23/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 09/22/2005 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. |
| 09/22/2005 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. |
| 09/22/2005 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 09/22/2005 | SPECIAL INSPECTION FOR SPECIAL MOMENT-RESISTING CONCRETE FRAME IS REQUIRED. |
| 09/22/2005 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
| 09/22/2005 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
| 09/22/2005 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. |
| 09/22/2005 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
| 07/27/2006 | Laith Alshami, ngineering and Floodplain Review, 07/27/2006 Show on the Grading Plan the trsh enclosure with inside clear dimension of 10' X 10' X 5" thick slab. |
Outstanding Inspections
Permit Status: Withdrwn
Permit Number: T05CM04401
Permite Description: NEW BANK
Total Outstanding Inspections - 30
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| EXCAVATION/LAYOUT REBAR & ZON | N/A | Not Inspected | ||
| STEM WALL/RETAINING WALL | N/A | Not Inspected | ||
| BUILDING PRE-SLAB | N/A | Not Inspected | ||
| REINFORCED MASONRY PRE-GROUT | N/A | Not Inspected | ||
| FRAMING | N/A | Not Inspected | ||
| BUILDING ABOVE CEILING | N/A | Not Inspected | ||
| U VALUE FOR WINDOW | N/A | Not Inspected | ||
| SHEET ROCK NAILING | N/A | Not Inspected | ||
| BUILDING - FINAL | N/A | Not Inspected | ||
| ELECTRIC - UFER | N/A | Not Inspected | ||
| ELECTRIC - UNDERGROUND | N/A | Not Inspected | ||
| ELECTRIC - INTERMEDIATE | N/A | Not Inspected | ||
| ELECTRIC - ABOVE CEILING | N/A | Not Inspected | ||
| ELECTRIC - CABLE DROP | N/A | Not Inspected | ||
| ELECTRIC - TEMPORARY SERVICE | N/A | Not Inspected | ||
| ELECTRIC - CONSTRUCTION POWER | N/A | Not Inspected | ||
| ELECTRIC - TEMP POWER FOR TEST | N/A | Not Inspected | ||
| ELECTRIC - FINAL | N/A | Not Inspected | ||
| OUTDOOR LIGHTING FINAL | N/A | Not Inspected | ||
| PLUMBING - ROUGH, SOIL | N/A | Not Inspected | ||
| PLUMBING - PRE SLAB | N/A | Not Inspected | ||
| PLUMBING - INTERMEDIATE | N/A | Not Inspected | ||
| PLUMBING - ABOVE CEILING | N/A | Not Inspected | ||
| PLUMBING - YARD WTR LINE/TEST | N/A | Not Inspected | ||
| PLUMBING - GAS PRESSURE TEST | N/A | Not Inspected | ||
| PLUMBING - SEWER HCS CONNECT | N/A | Not Inspected | ||
| PLUMBING - PROGRESS | N/A | Not Inspected | ||
| PLUMBING - FINAL | N/A | Not Inspected | ||
| MECHANICAL - ABOVE CEILING | N/A | Not Inspected | ||
| MECHANICAL - FINAL | N/A | Not Inspected |