Permit: T05CM04275
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
3443 E FORT LOWELL RD #101
Address NEW:
3443 E FORT LOWELL RD #101
Apply Date:
08/15/2005
Applicant:
N/A
Description:
TI: OFFICE
Architects:
- GOLDSTEIN, GENE
Contractors:
- ENVIRONMENTAL STRATEGIES INC ,
Permit Reviews
Permit Number - T05CM04275
Permit Status: C of o
Permit Description: TI: OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/15/2005 | PLANS OK TO SUBMIT - COMM | 08/25/2005 | COMPLETED |
| 08/25/2005 | 3RD PARTY REVIEW-COMMERCIAL TI | 09/13/2005 | COMPLETED |
| 09/13/2005 | POST 3RD PARTY REVIEW | 09/22/2005 | COMPLETED |
| 12/14/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 01/04/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM04275
Permit Status: C of o
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/15/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM04275
Permit Description: TI: OFFICE
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/31/2005 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | FOOTING ?? EXCLUDE 2 FOOTING AT FRONT ENTRANCE |
| 11/16/2005 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/21/2005 | SITE - SEWER | RMYERS | Approved | IVRS - Inspection :*SITE SEWER IS P.O.C TO BLDG DRAIN ABS UNDER SLAB FOR NEW TOILET ROOM OK LAV OK SINK OK OK TO COVER ALL AREAS |
| 11/21/2005 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
| 11/22/2005 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/22/2005 | ELECTRIC - INTERMEDIATE | RMAJUTA | Approved | IVRS - Inspection :* |
| 12/09/2005 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 12/09/2005 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR CELING TILES |
| 12/09/2005 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/10/2005 | PLUMBING - ABOVE CEILING | TRINIVJR | Approved | IVRS - Inspection :*ABOVE CEILING IS OK FOR GRID & TILE |
| 12/13/2005 | RIGHT OF WAY - FINAL | DLEE | Approved | PER EMAIL |
| 12/15/2005 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :*OK FOR FINAL C OF O |
| 12/15/2005 | FIRE - FINAL | LTHOMAS | Approved | |
| 12/15/2005 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 12/19/2005 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection :**PLBG FINAL IS OK OK FOR C OF O |
| 12/19/2005 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 12/22/2005 | ELECTRIC - FINAL | CCLEMENS | Approved | IVRS - Inspection :* |
| 12/27/2005 | BUILDING - FINAL | JCAGLE | Approved | IVRS - Inspection :* |
| 01/04/2006 | PERMIT FINALED | LJACKSON | Approved |