Permit: T05CM04161
Permit Details
Apply Date:
08/08/2005
Applicant:
PHILIP CARHUFF
Description:
NEW RETAIL SHELL
Contractors:
- CANYON BUILDING & DESIGN
Permit Reviews
Permit Number - T05CM04161
Permit Status: Final
Permit Description: NEW RETAIL SHELL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/16/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 06/21/2006 | COMPLETED |
| 08/08/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 08/08/2005 | COMPLETED |
| 08/08/2005 | 3RD PARTY REVIEW-COMMERCIAL | 10/18/2005 | COMPLETED |
| 10/18/2005 | POST 3RD PARTY REVIEW | 10/26/2005 | COMPLETED |
| 10/20/2005 | SITE | 10/26/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM04161
Permit Status: Final
Permit Description: NEW RETAIL SHELL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/08/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T05CM04161
Permit Description: NEW RETAIL SHELL
Total Completed Inspections - 44
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/16/2005 | ELECTRIC - UFER | RMAJUTA | Approved | IVRS - Inspection :* 1) 3/0 COPPER 20' PLUS CLAMPED TO REBAR |
| 12/22/2005 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/22/2005 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/28/2005 | ELECTRIC - UNDERGROUND | CCLEMENS | Approved | IVRS - Inspection :* 1) NEW SERVICE LOCATION AND NEW RACEWAY WIRING METHOD FOR SUB-PANEL FEEDERS NEED TO BE REVISED ON THE PLANS-OK TO COVER ELECTRICAL UNDER GROUND BASED ON REVISIONS BEING APPROVED |
| 12/28/2005 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :*ABS DWV UNDERSLAB OK TO COVER WATER TEST , ONE RISER TO TEN FEET 3 TIMES CONTRACTOR TO WRAP PIPE PRE P??? |
| 12/29/2005 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :*INCOMPLETE |
| 01/18/2006 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* |
| 02/27/2006 | ROOF NAILING | JCAGLE | Approved | IVRS - Inspection :* |
| 03/08/2006 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
| 03/14/2006 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection :* |
| 03/20/2006 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/27/2006 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/04/2006 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/12/2006 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* 1. RPPBP AND IRRIGATION BACKFLOW INSTALLED OK OK TO COVER |
| 04/27/2006 | SITE - SEWER | RMYERS | Approved | SITE SEWER 2" FORCED MAIN PER PLAN TO NEW HCS CONNECTION PROVIDED BY PIMA COUNTY OK TO COVER. |
| 05/02/2006 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 05/02/2006 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection :* |
| 05/02/2006 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 05/02/2006 | ELECTRIC - PROGRESS | CCLEMENS | Approved | IVRS - Inspection :* |
| 05/02/2006 | ELECTRIC - RECONNECT | CCLEMENS | Approved | IVRS - Inspection :* |
| 05/02/2006 | ELECTRIC - SERVICE UPGRADE | CCLEMENS | Approved | IVRS - Inspection :* |
| 05/02/2006 | ELECTRIC - TEMP POWER FOR TEST | CCLEMENS | Approved | IVRS - Inspection :* |
| 05/02/2006 | ELECTRIC - ABOVE CEILING | CCLEMENS | Approved | IVRS - Inspection :* |
| 05/02/2006 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection :* |
| 05/03/2006 | PLUMBING - BACK WATER VALVE | RMYERS | Approved | IVRS - Inspection :* 1. NO BACKWATER VALVE REQUIRED PUMPED WASTE TO HCS CONNECTION. |
| 05/10/2006 | ELECTRIC - CONSTRUCTION POWER | RMAJUTA | Approved | IVRS - Inspection :* |
| 05/25/2006 | NPPO - FINAL | ACONNOR | Approved | |
| 05/25/2006 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 05/25/2006 | SIGN - FINAL | JSONKIN | Approved | IVRS - Inspection :* |
| 05/26/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED FOR UNITS #100, 118, 136, 154, 172 & 190 PER C. CLEMENS |
| 05/31/2006 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
| 06/05/2006 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* 1. CORRECTIONS MADE OK 2. PLUMBING FINAL OK |
| 06/05/2006 | FIRE - FINAL | LTHOMAS | Approved | |
| 06/05/2006 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
| 06/05/2006 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
| 06/05/2006 | MECHANICAL - PROGRESS | CWILLIAM | Approved | IVRS - Inspection :* |
| 06/06/2006 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 06/06/2006 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
| 06/06/2006 | ELECTRIC - FINAL | CCLEMENS | Approved | IVRS - Inspection :* |
| 06/06/2006 | ELECTRIC - OUTDOOR LIGHTING | CCLEMENS | Approved | IVRS - Inspection :* |
| 06/06/2006 | ELECTRIC - INTERMEDIATE | CCLEMENS | Approved | IVRS - Inspection :* |
| 06/06/2006 | ELECTRIC - CABLE DROP | CCLEMENS | Approved | IVRS - Inspection :* |
| 06/06/2006 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 05/08/2007 | PERMIT FINALED | LJACKSON | Approved |