Permit: T05CM03856
Permit Details
Apply Date:
07/22/2005
Applicant:
N/A
Description:
NEW: CELL TOWER
Contractors:
- OPTIMA NETWORK SERVICES INC
Permit Reviews
Permit Number - T05CM03856
Permit Status: Final
Permit Description: NEW: CELL TOWER
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/22/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 07/22/2005 | COMPLETED |
07/22/2005 | 3RD PARTY REVIEW-CELL TOWER/ANTENNAS | 08/16/2005 | COMPLETED |
08/19/2005 | POST 3RD PARTY REVIEW | 09/29/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM03856
Permit Status: Final
Permit Description: NEW: CELL TOWER
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/22/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T05CM03856
Permit Description: NEW: CELL TOWER
Total Completed Inspections - 8
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/25/2006 | EXCAVATION/LAYOUT REBAR & ZON | JCAGLE | Approved | IVRS - Inspection :* |
01/30/2006 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* |
01/30/2006 | ELECTRIC - UNDERGROUND | RSUBA | Approved | IVRS - Inspection :* |
04/25/2006 | BUILDING - FINAL | JCAGLE | Approved | IVRS - Inspection :* |
04/25/2006 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
04/26/2006 | BUILDING PRE-SLAB | JCAGLE | Approved | |
04/26/2006 | ELECTRIC - UFER | DSANTACR | Approved | |
08/01/2006 | PERMIT FINALED | JMORALES | Approved |