Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
DUPLEX NEW
Apply Date:
07/13/2005
Applicant:
GOLDSTEIN CONSTRUCTION MANAGEMEN
Description:
DUPLEX:TD#16-36-37
Contractors:
  • GOLDSTEIN CONSTRUCTION MANAGEMEN

Permit Reviews

Permit Number - T05CM03713
Permit Status: C of o
Permit Description: DUPLEX:TD#16-36-37
Start Date Submittal Complete Date Status  
07/13/2005 RESIDENTIAL BLDG-MODEL PLAN/ENGINE/WALK THRU 07/14/2005 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T05CM03713
Permit Status: C of o
Permit Description: DUPLEX:TD#16-36-37
Total Outstanding Activity Conditions - 1
Date Name
07/13/2005 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T05CM03713
Permit Description: DUPLEX:TD#16-36-37
Total Completed Inspections - 29
Date Description Inspector Results Comments
10/28/2005 PLUMBING - ROUGH, SOIL RRICH Approved IVRS - Inspection :*WATER TEST UNDERGROUND FROM BUILDING INTERIOR THRU 2 WAY CLEANOUT OK
12/19/2005 ELECTRIC - UFER RMAJUTA Approved IVRS - Inspection :*USE ONLY BRASS CLAMPS FOR CONNECTION TO REBAR
12/19/2005 BUILDING PRE-SLAB LHANLY Approved IVRS - Inspection :*
12/19/2005 STEM WALL/RETAINING WALL LHANLY Approved IVRS - Inspection :*
12/19/2005 EXCAVATION/LAYOUT REBAR & ZON LHANLY Approved IVRS - Inspection :*
06/12/2006 PLUMBING - ABOVE CEILING RRICH Approved IVRS - Inspection :*
06/14/2006 PLUMBING - INTERMEDIATE RLEDONNE Approved IVRS - Inspection :*
06/14/2006 ELECTRIC - ABOVE CEILING RSUBA Approved IVRS - Inspection :*
06/14/2006 ELECTRIC - INTERMEDIATE RSUBA Approved IVRS - Inspection :*
06/19/2006 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
06/19/2006 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
OK FOR SHEETROCK
06/20/2006 FRAMING GDABBS Approved IVRS - Inspection :*
OK TO INSULATE
06/20/2006 STUCCO MESH GDABBS Approved IVRS - Inspection :*
06/22/2006 ROOF NAILING LHANLY Approved IVRS - Inspection :*
07/07/2006 SHEET ROCK NAILING GDABBS Approved IVRS - Inspection :*
09/19/2006 PLUMBING - SEWER HCS CONNECT RRICH Approved IVRS - Inspection :*
09/19/2006 ELECTRIC - TEMPORARY SERVICE RMAJUTA Approved IVRS - Inspection :*
09/20/2006 TEP CLEARANCE - AM JWEATHER Approved TEC CLEARED PER R. MAJUTA
10/12/2006 PLUMBING - YARD WTR LINE/TEST RRICH Approved THIS INSPECTION FOR SHOWER PANS OK
10/26/2006 PLUMBING - FINAL RRICH Approved IVRS - Inspection :*
10/27/2006 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
10/30/2006 MECHANICAL - UNDERGROUND JMILITEL Approved
10/30/2006 SITE - SEWER RSUBA Approved
10/30/2006 ELECTRIC - UNDERGROUND RSUBA Approved
10/30/2006 ELECTRIC - FINAL RSUBA Approved PER INSP COPY
10/30/2006 ELECTRIC - CABLE DROP RSUBA Approved
10/30/2006 U VALUE FOR WINDOW GDABBS Approved PER BU FINAL
10/30/2006 BUILDING ABOVE CEILING GDABBS Approved PER BU FINAL
10/30/2006 BUILDING - FINAL GDABBS Approved PER INSP COPY

Documents

File Name Document Type  
None CONSTRPLANS VIEW
None DOCUMENTS VIEW
None CERT OF OCC VIEW