Permit: T05CM03713
Permit Details
Status:
C of o
Type:
DUPLEX NEW
Address:
8673 E PLACITA MORELIA #01
Address NEW:
8673 E PLACITA MORELIA #01
Apply Date:
07/13/2005
Applicant:
GOLDSTEIN CONSTRUCTION MANAGEMEN
Description:
DUPLEX:TD#16-36-37
Contractors:
- GOLDSTEIN CONSTRUCTION MANAGEMEN
Permit Reviews
Permit Number - T05CM03713
Permit Status: C of o
Permit Description: DUPLEX:TD#16-36-37
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/13/2005 | RESIDENTIAL BLDG-MODEL PLAN/ENGINE/WALK THRU | 07/14/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM03713
Permit Status: C of o
Permit Description: DUPLEX:TD#16-36-37
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/13/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM03713
Permit Description: DUPLEX:TD#16-36-37
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/28/2005 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :*WATER TEST UNDERGROUND FROM BUILDING INTERIOR THRU 2 WAY CLEANOUT OK |
| 12/19/2005 | ELECTRIC - UFER | RMAJUTA | Approved | IVRS - Inspection :*USE ONLY BRASS CLAMPS FOR CONNECTION TO REBAR |
| 12/19/2005 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :* |
| 12/19/2005 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection :* |
| 12/19/2005 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* |
| 06/12/2006 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
| 06/14/2006 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
| 06/14/2006 | ELECTRIC - ABOVE CEILING | RSUBA | Approved | IVRS - Inspection :* |
| 06/14/2006 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* |
| 06/19/2006 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 06/19/2006 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* OK FOR SHEETROCK |
| 06/20/2006 | FRAMING | GDABBS | Approved | IVRS - Inspection :* OK TO INSULATE |
| 06/20/2006 | STUCCO MESH | GDABBS | Approved | IVRS - Inspection :* |
| 06/22/2006 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection :* |
| 07/07/2006 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 09/19/2006 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
| 09/19/2006 | ELECTRIC - TEMPORARY SERVICE | RMAJUTA | Approved | IVRS - Inspection :* |
| 09/20/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER R. MAJUTA |
| 10/12/2006 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | THIS INSPECTION FOR SHOWER PANS OK |
| 10/26/2006 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
| 10/27/2006 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 10/30/2006 | MECHANICAL - UNDERGROUND | JMILITEL | Approved | |
| 10/30/2006 | SITE - SEWER | RSUBA | Approved | |
| 10/30/2006 | ELECTRIC - UNDERGROUND | RSUBA | Approved | |
| 10/30/2006 | ELECTRIC - FINAL | RSUBA | Approved | PER INSP COPY |
| 10/30/2006 | ELECTRIC - CABLE DROP | RSUBA | Approved | |
| 10/30/2006 | U VALUE FOR WINDOW | GDABBS | Approved | PER BU FINAL |
| 10/30/2006 | BUILDING ABOVE CEILING | GDABBS | Approved | PER BU FINAL |
| 10/30/2006 | BUILDING - FINAL | GDABBS | Approved | PER INSP COPY |