Permit: T05CM03372
Permit Details
Apply Date:
07/06/2005
Applicant:
BAY CITIES INVESTMENTS
Description:
TOWNHOUSE:TD#16-15-25
Contractors:
- CAPITAL CONSTRUCTION L L C
Permit Reviews
Permit Number - T05CM03372
Permit Status: C of o
Permit Description: TOWNHOUSE:TD#16-15-25
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/06/2005 | RESIDENTIAL BLDG-MODEL PLAN/ENGINE/WALK THRU | 07/06/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM03372
Permit Status: C of o
Permit Description: TOWNHOUSE:TD#16-15-25
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/06/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM03372
Permit Description: TOWNHOUSE:TD#16-15-25
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/27/2005 | STEM WALL/RETAINING WALL | AMATHIES | Approved | IVRS - Inspection :* |
| 01/05/2006 | BUILDING - PROGRESS | AMATHIES | Approved | IVRS - Inspection :* |
| 01/19/2006 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | IVRS - Inspection :*SOIL WATER TEST IS OK HCS CONNECTION IS OK NOTE: CONTRACTOR SHALL USE CLEAN FILL FOR BACKFILL |
| 01/19/2006 | PLUMBING - SEWER HCS CONNECT | TRINIVJR | Approved | IVRS - Inspection :* |
| 01/20/2006 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :* |
| 01/20/2006 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* |
| 01/20/2006 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
| 01/20/2006 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
| 02/21/2006 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* CONTRACTOR RESPONSIBLE TO PROVIDE CLEAN FILL IN ACCORDANCE W/MANUFACTURERS REQUIREMENTS. |
| 03/02/2006 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/02/2006 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/02/2006 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/03/2006 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 03/10/2006 | U VALUE FOR WINDOW | LHANLY | Approved | IVRS - Inspection :* |
| 03/10/2006 | STUCCO MESH | LHANLY | Approved | IVRS - Inspection :* |
| 03/10/2006 | FRAMING | LHANLY | Approved | IVRS - Inspection :* |
| 03/17/2006 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* 1) OK CABLE DROP U.G. |
| 03/22/2006 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | IVRS - Inspection :* |
| 03/23/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER D. SANTACRUZ |
| 03/28/2006 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/30/2006 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection :* |
| 04/06/2006 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 04/07/2006 | PLUMBING - FINAL | BBENEDON | Approved | |
| 04/07/2006 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
| 04/10/2006 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/11/2006 | PERMIT FINALED | BFLORES | Approved | |
| 04/11/2006 | PLUMBING - INTERMEDIATE | BBENEDON | Approved |