Permit: T05CM01888
Permit Details
Apply Date:
04/28/2005
Applicant:
GRASKIN ENG/JOEL SCHULMAN
Description:
TI:RETAIL
Architects:
- GRASKIN, KENNETH A
Contractors:
- BOVENKAMP INC
Permit Reviews
Permit Number - T05CM01888
Permit Status: C of o
Permit Description: TI:RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/28/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 06/06/2005 | COMPLETED |
06/06/2005 | 3RD PARTY REVIEW-COMMERCIAL TI | 06/24/2005 | COMPLETED |
06/24/2005 | POST 3RD PARTY REVIEW | 09/23/2005 | COMPLETED |
09/23/2005 | POST 3RD PARTY REVIEW | 10/28/2005 | COMPLETED |
12/29/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 01/06/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM01888
Permit Status: C of o
Permit Description: TI:RETAIL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/28/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM01888
Permit Description: TI:RETAIL
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/09/2005 | ELECTRIC - UNDERGROUND | RMAJUTA | Approved | IVRS - Inspection :*IN SLAB POWER & DATA |
11/10/2005 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :*PLEASE HAVE YOUR SUITE NUMBER ADDED TO YOUR PERMIT BY THE NEXT INSPECTION ABS DWV UNDERSLAB OK WATER TEST ONE RISER TO TEN FEET OK OK TO COVER |
11/22/2005 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :*OK TO COVER WALLS NEED TO SEE CLOSET FLANGES AND OVERHEAD HANGERS |
11/22/2005 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :*EXCLUDES BLOCKING IN RESTROOM |
11/22/2005 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :*EXCLUDES RESTROOMS AND SEPARATIONS WALL |
12/15/2005 | ELECTRIC - INTERMEDIATE | CCLEMENS | Approved | IVRS - Inspection :*TALKED WITH KELLY ABOUT SERVICE PERMIT |
12/15/2005 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection :*SUBMIT NEW PLAN FOR APPROVAL & ENGINEERS STAMP |
12/16/2005 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* 1) OK TO COVER ALL AREAS 2) CLOSET FLANGES OK |
01/05/2006 | ELECTRIC - CABLE DROP | CCLEMENS | Approved | IVRS - Inspection :* |
01/06/2006 | TEP CLEARANCE - AM | JKOZUCH | Approved | ECO |
01/09/2006 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :*PLUMBING FINAL OK |
01/09/2006 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection :* |
01/12/2006 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
01/26/2006 | RIGHT OF WAY - FINAL | MOTERO | Approved | PER EMAIL |
01/26/2006 | FIRE - FINAL | LTHOMAS | Approved | |
01/26/2006 | ENGINEERING - FINAL | MRUSSO | Approved | |
01/26/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
01/30/2006 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :*LETTER FROM ARCHITECT DELETES W/OCCUPANTS OK TO ACCEPT WITHOUT ACCESSORIES |
01/31/2006 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
02/01/2006 | ELECTRIC - FINAL | CCLEMENS | Approved | |
02/01/2006 | ELECTRIC - TEMPORARY SERVICE | CCLEMENS | Approved | |
02/01/2006 | ELECTRIC - ABOVE CEILING | CCLEMENS | Approved | |
02/01/2006 | PERMIT FINALED | DROBEY | Approved | |
02/01/2006 | FIRE SPKLR - FINAL | LTHOMAS | Approved |