Permit: T05CM00836
Permit Details
Apply Date:
02/24/2005
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
TI:DENTAL OFFICE
Contractors:
- CAYLOR CONSTRUCTION COMPANY , RO
Permit Reviews
Permit Number - T05CM00836
Permit Status: C of o
Permit Description: TI:DENTAL OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/24/2005 | COMMERCIAL TI | 03/11/2005 | COMPLETED |
03/11/2005 | 3RD PARTY REVIEW-COMMERCIAL TI | 03/24/2005 | COMPLETED |
03/24/2005 | POST 3RD PARTY REVIEW | 04/06/2005 | COMPLETED |
05/02/2005 | OTHER | 05/02/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM00836
Permit Status: C of o
Permit Description: TI:DENTAL OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/24/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM00836
Permit Description: TI:DENTAL OFFICE
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/28/2005 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* 1) NO TRAP PRIMER CONNECION ON FLOOR SINK AS REQUIRED BY PLAN. 2) PLUMBER TO PIPE PRIMER EXPOSED ABOVE GRADE.OK FOR CONCRETE. |
05/13/2005 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* OK WALLS AND HARD CEILING |
05/24/2005 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* 1) ABS DWV THRU ROOF OK 2) WATER TEST OK 3) WATER PIPING OK 4) CLOSET FLANGES OK 5) OK TO COVER ALL AREAS |
05/24/2005 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
05/25/2005 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1) INSPECTED SUPPLY AND EXHAUST IN RESTROOMS 2) CHECKED CONDENSATE DRAIN LINES 3) OK FOR SHEET ROCK |
05/30/2005 | PLUMBING - GAS PRESSURE TEST | TRINIVJR | Approved | IVRS - Inspection :* 1) GAS PRESSURE TEST IS OK 2) THIS INSPECTION IS FOR THE GAS PACKS ON ROOF ONLY |
05/31/2005 | SHEET ROCK NAILING | BSTEVENS | Approved | IVRS - Inspection :* |
06/07/2005 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* INSPECTED MECHANICAL ABOVE CEILING OK FOR CEILING TILES |
06/13/2005 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | |
06/13/2005 | ELECTRIC - TEMPORARY SERVICE | RHOLLAND | Approved | IVRS - Inspection :* OK TEMP POWER FOR TEST |
06/14/2005 | FIRE - FINAL | LTHOMAS | Approved | |
06/14/2005 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
06/14/2005 | TEP CLEARANCE - AM | JKOZUCH | Approved | ECO PER MORALES |
06/29/2005 | ENGINEERING - FINAL | JBRUCKME | Approved | |
06/29/2005 | PLUMBING - PROGRESS | TRINIVJR | Approved | IVRS - Inspection :* |
06/29/2005 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
06/29/2005 | BUILDING - PROGRESS | BSTEVENS | Approved | IVRS - Inspection :* |
06/30/2005 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* CORRECTIONS HAVE BEEN MADE. OK FOR FINAL C OF O |
06/30/2005 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection :* PLBG FINAL IS OK. OK FOR C OF O |
06/30/2005 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
06/30/2005 | FRAMING | BSTEVENS | Approved | IVRS - Inspection :* |
07/01/2005 | PLUMBING - GAS PRESS TEST FNL | TRINIVJR | Approved | FINAL CONNECTIONS TO ALL EQUIPMENT IS OK |
07/05/2005 | MEDICAL GAS - FINAL | JMILITEL | Approved | |
07/05/2005 | MEDICAL GAS - FINAL | JMILITEL | Approved | |
07/05/2005 | MEDICAL - GAS/TEST INTERMED | JMILITEL | Approved | IVRS - Inspection :* |
07/06/2005 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
07/06/2005 | ELECTRIC - PROGRESS | RHOLLAND | Approved | IVRS - Inspection :* |
07/07/2005 | BUILDING - FINAL | BSTEVENS | Approved | IVRS - Inspection :* |