Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
6400 S COMMERCE CT
Apply Date:
10/13/2004
Applicant:
A P N BUILDERS
Description:
SELF STORAGE & OFFICE: BLDG 6
Contractors:
  • A P N BUILDERS INC ,

Permit Reviews

Permit Number - T04CM04576
Permit Status: C of o
Permit Description: SELF STORAGE & OFFICE: BLDG 6
Start Date Submittal Complete Date Status  
01/19/2005 POST 3RD PARTY REVIEW 01/21/2005 COMPLETED Review Details
01/31/2005 POST 3RD PARTY REVIEW 02/15/2005 COMPLETED Review Details
02/17/2005 RESUBMITTAL 03/01/2005 COMPLETED Review Details
07/06/2005 3RD PARTY REVIEW-REVISION/OTHER 07/06/2005 COMPLETED Review Details
10/13/2004 PLANS OK TO SUBMIT - COMM 10/15/2004 COMPLETED Review Details
10/15/2004 3RD PARTY REVIEW-COMMERCIAL TI 01/19/2005 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T04CM04576
Permit Status: C of o
Permit Description: SELF STORAGE & OFFICE: BLDG 6
Total Outstanding Activity Conditions - 1
Date Name
10/13/2004 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T04CM04576
Permit Description: SELF STORAGE & OFFICE: BLDG 6
Total Completed Inspections - 45
Date Description Inspector Results Comments
03/22/2005 STEM WALL/RETAINING WALL AMATHIES Approved
03/31/2005 PLUMBING - ROUGH, SOIL TRINIVJR Approved IVRS - Inspection :* 1) SOIL WATER TEST IS OK. 2) NOTE: BLDG DRAIN IS STUBBED OUT@ TWO WAY C.O ONLY. 3) OK TO BACKFILL TRENCH.
04/13/2005 EXCAVATION/LAYOUT REBAR & ZON AMATHIES Approved IVRS - Inspection :*
05/26/2005 BUILDING PRE-SLAB AMATHIES Approved IVRS - Inspection :* / APPROVED 2ND FLOOR
06/28/2005 PLUMBING - ABOVE CEILING TRINIVJR Approved IVRS - Inspection :* 1) DWV WATER TEST IS OK. 2) OVERHEAD WATER DISTRIBUTION IS OK. 3) ALL CORRECTION HAVE BEEN MADE.
06/28/2005 PLUMBING - INTERMEDIATE TRINIVJR Approved IVRS - Inspection :*
06/28/2005 SITE - SEWER TRINIVJR Approved IVRS - Inspection :*
06/28/2005 PLUMBING - SEWER HCS CONNECT TRINIVJR Approved IVRS - Inspection :*
06/28/2005 PLUMBING - ABOVE CEILING TRINIVJR Approved IVRS - Inspection :
See detailed listing on site.| 999*
06/28/2005 ROOF NAILING AMATHIES Approved IVRS - Inspection :*
07/15/2005 FRAMING AMATHIES Approved IVRS - Inspection :*
07/15/2005 EXT METAL CLIPS/EXT SHEATHING AMATHIES Approved IVRS - Inspection :*
07/26/2005 ELECTRIC - UNDERGROUND DSANTACR Approved IVRS - Inspection :*
1) OK UNDERGROUND
08/04/2005 BUILDING ABOVE CEILING AMATHIES Approved IVRS - Inspection :*
08/10/2005 ELECTRIC - INTERMEDIATE DSANTACR Approved IVRS - Inspection :*
08/19/2005 SHEET ROCK NAILING AMATHIES Approved IVRS - Inspection :*
08/19/2005 U VALUE FOR WINDOW AMATHIES Approved IVRS - Inspection :*
08/29/2005 STUCCO MESH AMATHIES Approved IVRS - Inspection :*
09/01/2005 ELECTRIC - UFER DSANTACR Approved IVRS - Inspection :*
09/13/2005 ELECTRIC - TEMPORARY SERVICE DSANTACR Approved
09/13/2005 ELECTRIC - CABLE DROP DSANTACR Approved IVRS - Inspection :*
1) OK TO CLEAR ECO SUBJECT TO BOND POSTING AND RECEIPT OF LETTER OF TORQUE
09/21/2005 ELECTRIC - TEMP POWER FOR TEST DSANTACR Approved CLEARANCE SENT TO TEP FOR TEMP POWER
09/22/2005 TEP CLEARANCE - AM JWEATHER Approved OK ECO PER SANTACRUZ FOR BLDG 6
09/26/2005 PLUMBING - YARD WTR LINE/TEST RRICH Approved IVRS - Inspection :*
09/26/2005 MECHANICAL - ABOVE CEILING CWILLIAM Approved IVRS - Inspection :*
09/26/2005 MECHANICAL - INTERMEDIATE CWILLIAM Approved IVRS - Inspection :*
09/28/2005 PLUMBING - FINAL RRICH Approved IVRS - Inspection :* INTERNAL BACKFLOW CERTIFICATION FOR LANDSCAPING
09/28/2005 MECHANICAL - FINAL CWILLIAM Approved IVRS - Inspection :*
09/28/2005 FIRE - HYDRANTS LTHOMAS Approved
09/28/2005 FIRE SPKLR - FINAL LTHOMAS Approved
09/28/2005 FIRE SPKLR - OH PIPING & HYDRO LTHOMAS Approved
09/28/2005 FIRE SPKLR - UG PIPING FLUSH LTHOMAS Approved
09/28/2005 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved
09/28/2005 FIRE - FINAL LTHOMAS Approved
09/29/2005 ELECTRIC - FINAL DSANTACR Approved IVRS - Inspection :*
09/29/2005 OUTDOOR LIGHTING FINAL DSANTACR Approved IVRS - Inspection :*
09/29/2005 ELECTRIC - OUTDOOR LIGHTING DSANTACR Approved IVRS - Inspection :*
09/29/2005 ELECTRIC - ABOVE CEILING DSANTACR Approved IVRS - Inspection :*
09/29/2005 NPPO - FINAL ACONNOR Approved Ok for Temp. C of O

For approval

1) Complete all site work.

2) Revise development plan into Phase 1&2.

3) Dust control for undeveloped portion.

4) Address Engineering comments.
09/29/2005 LANDSCAPE - FINAL ACONNOR Approved Ok for Temp. C of O

For approval

1) Complete all site work.

2) Revise development plan into Phase 1&2.

3) Dust control for undeveloped portion.

4) Address Engineering comments.
09/30/2005 SIGN - FINAL RDEAR Approved IVRS - Inspection :*
10/03/2005 RIGHT OF WAY - FINAL LLOPEZ Approved PER EMAIL
10/04/2005 BUILDING - FINAL AMATHIES Approved IVRS - Inspection :*OK TEMP C OF O
10/04/2005 ENGINEERING - FINAL MAVERY Approved Approved for Temp C of O.
Punch-list for Final
1- Complete all painting.
2- Clean all silt off street and construction debris.
3- Install truncated domes on all H.C. ramps.
4- Install splash pads on all roof drains.
5- Grout and paint trash encloser bollards.
04/13/2006 PERMIT FINALED BGRANT Approved