Permit: T04CM03998
Permit Details
Apply Date:
09/01/2004
Applicant:
N/A
Description:
WATER BOOSTER STATION
Contractors:
- P AND H CONTRACTING INC ,
Permit Reviews
Permit Number - T04CM03998
Permit Status: Final
Permit Description: WATER BOOSTER STATION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/01/2004 | PLANS OK TO SUBMIT - COMM | 09/17/2004 | COMPLETED |
| 09/01/2004 | PLANS OK TO SUBMIT - SITE | 09/17/2004 | COMPLETED |
| 09/17/2004 | COMMERCIAL NEW | 10/14/2004 | COMPLETED |
| 09/17/2004 | SITE | 10/14/2004 | COMPLETED |
| 11/10/2004 | RESUBMITTAL | 12/09/2004 | COMPLETED |
| 11/10/2004 | RESUBMITTAL - SITE ALL | 12/09/2004 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T04CM03998
Permit Status: Final
Permit Description: WATER BOOSTER STATION
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/01/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T04CM03998
Permit Description: WATER BOOSTER STATION
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/09/2005 | NPPO PRE PERMIT INSPECTION | ACONNOR | Approved | |
| 03/23/2005 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* APPROVED |
| 03/25/2005 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/11/2005 | REINFORCED MASONRY PRE-GROUT | AMATHIES | Approved | IVRS - Inspection :* |
| 07/07/2005 | ELECTRIC - UNDERGROUND | MCAPISTR | Approved | IVRS - Inspection :* |
| 07/08/2005 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 07/08/2005 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | |
| 07/08/2005 | NPPO - FINAL | ACONNOR | Approved | |
| 07/08/2005 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 07/11/2005 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* 1) ALL BOOSTER PUMPS AND RELATED PIPING INSPECTED BY TUCSON WATER 2) NO PLUMBING TO INSPECT |
| 07/11/2005 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 07/15/2005 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* OK TO CLEAR ECO OK TO CLEAR CEC |
| 07/15/2005 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 07/15/2005 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 07/15/2005 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
| 07/18/2005 | MECHANICAL - UNDERGROUND | JMILITEL | Approved | |
| 07/18/2005 | EXCAVATION/LAYOUT REBAR & ZON | AMATHIES | Approved | |
| 07/18/2005 | FRAMING | AMATHIES | Approved | |
| 07/18/2005 | BUILDING - FINAL | AMATHIES | Approved | IVRS - Inspection :* |
| 07/18/2005 | TEP CLEARANCE - AM | JKOZUCH | Approved | |
| 01/10/2006 | PERMIT FINALED | LJACKSON | Approved |