Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
101 W IRVINGTON RD 10
Apply Date:
08/26/2004
Applicant:
ENCH, CURTIS ANDREW
Description:
SENIOR CENTER:NEW ,MOVE IN FURNITURE & EQIP ONLY
Architects:
  • ENCH, CURTIS ANDREW
Contractors:
  • SUNDT CONSTRUCTION

Outstanding Activity Conditions

Permit Number - T04CM03923
Permit Status: C of o
Permit Description: SENIOR CENTER:NEW ,MOVE IN FURNITURE & EQIP ONLY
Total Outstanding Activity Conditions - 1
Date Name
08/26/2004 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T04CM03923
Permit Description: SENIOR CENTER:NEW ,MOVE IN FURNITURE & EQIP ONLY
Total Completed Inspections - 45
Date Description Inspector Results Comments
03/15/2005 ELECTRIC - UFER DSANTACR Approved IVRS - Inspection :*
04/22/2005 PLUMBING - ROUGH, SOIL TRINIVJR Approved IVRS - Inspection :*
06/27/2005 ELECTRIC - INTERMEDIATE RMAJUTA Approved IVRS - Inspection :*
07/14/2005 PLUMBING - GAS PRESSURE TEST TRINIVJR Approved IVRS - Inspection :* 1) GAS PRESSURE TEST IS OK. 2) RWL WATER TEST IS OK AS NOTED ON PLAN ONLY.
07/26/2005 PLUMBING - YARD WTR LINE/TEST TRINIVJR Approved IVRS - Inspection :*
1) FINAL CONNECTIONS TO BACKFLOW PREVENTER IS OK
2) OK TO BACKFILL TRENCH
08/30/2005 PLUMBING - ABOVE CEILING TRINIVJR Approved IVRS - Inspection :*
1) ABOVE CEILING IS OK FOR GRID AND TILE
08/30/2005 BUILDING ABOVE CEILING AMATHIES Approved IVRS - Inspection :*
09/01/2005 ELECTRIC - ABOVE CEILING DSANTACR Approved IVRS - Inspection :*
1) FOR TEMP POWER FOR TEST
2) PROVIDE LETTER OF TORQUE
3) CLOSE UP PANEL COVERS
09/02/2005 ELECTRIC - TEMP POWER FOR TEST DSANTACR Approved IVRS - Inspection :*
1) OK TO CLEAR TEMP POWER FOR TEST
2) ONLY AUTHORIZED PERSONEL TO HAVE ACCESS TO ELECTRICAL EQUIPMENT
09/06/2005 TEP CLEARANCE - AM RMAJUTA Approved OK TEMP POWER PER SANTA CRUZ
09/09/2005 MECHANICAL - ABOVE CEILING CWILLIAM Approved IVRS - Inspection :*
1) EXHAUST 8" X 8" DUCT UP THRU ROOF OK
2) OK TO WRAP
10/14/2005 ELECTRIC - CABLE DROP DSANTACR Approved IVRS - Inspection :*
10/14/2005 ELECTRIC - UNDERGROUND DSANTACR Approved IVRS - Inspection :*
10/14/2005 OUTDOOR LIGHTING FINAL DSANTACR Approved IVRS - Inspection :*
10/14/2005 ELECTRIC - FINAL DSANTACR Approved IVRS - Inspection :*
10/14/2005 FIRE SPKLR - OH PIPING & HYDRO LTHOMAS Approved
10/14/2005 FIRE SPKLR - UG PIPING FLUSH LTHOMAS Approved
10/14/2005 FIRE SPKLR - UG, PIPING, HYDRO LLAKEY Approved
10/14/2005 FIRE SPKLR - FINAL LTHOMAS Approved
10/17/2005 SHEET ROCK NAILING AMATHIES Approved IVRS - Inspection :*
10/17/2005 FRAMING AMATHIES Approved IVRS - Inspection :*
10/17/2005 ROOF NAILING AMATHIES Approved IVRS - Inspection :*
10/17/2005 REINFORCED MASONRY PRE-GROUT AMATHIES Approved IVRS - Inspection :*
10/17/2005 STEM WALL/RETAINING WALL AMATHIES Approved IVRS - Inspection :*
10/17/2005 BUILDING PRE-SLAB AMATHIES Approved IVRS - Inspection :*
10/17/2005 U VALUE FOR WINDOW AMATHIES Approved IVRS - Inspection :*
10/17/2005 EXCAVATION/LAYOUT REBAR & ZON AMATHIES Approved IVRS - Inspection :*
10/17/2005 PLUMBING - SEWER HCS CONNECT RRICH Approved IVRS - Inspection :*
10/17/2005 PLUMBING - ROOF DRAINS RRICH Approved IVRS - Inspection :*
10/17/2005 PLUMBING - INTERMEDIATE RRICH Approved IVRS - Inspection :*
10/17/2005 MECHANICAL - FINAL CWILLIAM Approved IVRS - Inspection :*
10/17/2005 MECHANICAL - HOOD SYSTEMS CWILLIAM Approved IVRS - Inspection :*
10/17/2005 MECHANICAL - HOODS CWILLIAM Approved IVRS - Inspection :*
10/19/2005 PLUMBING - GAS PRESS TEST FNL RRICH Approved IVRS - Inspection :*
10/19/2005 BUILDING - FINAL AMATHIES Approved OK FOR TEMP C OF O
10/20/2005 SIGN - FINAL JYBARRA Approved IVRS - Inspection :* SIGN NOT ALLOWED ON ROOF LINE; MUST REMOVE SIGN; TEMP C/O ONLY
10/21/2005 RIGHT OF WAY - FINAL MFLICK Approved Partial for temp CO only.
10/28/2005 FIRE - FINAL LTHOMAS Approved
10/28/2005 FIRE - KITCHEN EXH HOOD FINAL LTHOMAS Approved
11/22/2005 ENGINEERING - FINAL MAVERY Approved
11/22/2005 NPPO - FINAL ACONNOR Approved
11/22/2005 LANDSCAPE - FINAL ACONNOR Approved
12/01/2005 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
12/31/2008 MECHANICAL - INTERMEDIATE CWILLIAM Approved PER MECH FINAL BY CWILLIAM 10/17/05
01/02/2009 PERMIT FINALED LJACKSON Approved

Documents

File Name Document Type  
TEMP C OF O_10-21-2005.TIF CERT OF OCC VIEW
MODELENERGYCALCS.TIF DOCUMENTS VIEW
STRUCCALC.TIF DOCUMENTS VIEW
STRUCCALCSUPPLEMENT.TIF DOCUMENTS VIEW
None DOCUMENTS VIEW
None SIGNS VIEW