Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T04CM03459
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
3675 E BRITANNIA DR
Address NEW:
3675 E BRITANNIA DR
Apply Date:
07/27/2004
Applicant:
OPUS SOUTHWEST CONSTRUCTION CORP
Description:
TI:OFFICE
Contractors:
- OPUS SOUTHWEST CONSTRUCTION CORP
Permit Reviews
Permit Number - T04CM03459
Permit Status: C of o
Permit Description: TI:OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/14/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 04/20/2005 | COMPLETED |
| 07/27/2004 | PLANS OK TO SUBMIT - 3RD PARTY | 07/27/2004 | COMPLETED |
| 07/27/2004 | 3RD PARTY REVIEW-COMMERCIAL TI | 09/07/2004 | COMPLETED |
| 09/07/2004 | POST 3RD PARTY REVIEW | 09/10/2004 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T04CM03459
Permit Status: C of o
Permit Description: TI:OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/27/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T04CM03459
Permit Description: TI:OFFICE
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/27/2004 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* |
| 11/16/2004 | PLUMBING - INTERMEDIATE | TRINIVJR | Approved | IVRS - Inspection :*/SOIL WATER TEST FOR DWV @ WEST RESTROOM IS OK |
| 11/18/2004 | MECHANICAL - PROGRESS | CWILLIAM | Approved | IVRS - Inspection :* |
| 11/18/2004 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection :* |
| 11/24/2004 | FRAMING | AMATHIES | Approved | IVRS - Inspection :* |
| 12/01/2004 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :*/ 1) OK WALLS, HARD LIDS 2) CALL FOR ABOVE CEILINGS WHEN GRID/LIGHTS INSTALLED |
| 12/01/2004 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 12/06/2004 | PLUMBING - PROGRESS | TRINIVJR | Approved | IVRS - Inspection :*/OK FOR TEMP POWER |
| 12/08/2004 | SHEET ROCK NAILING | AMATHIES | Approved | IVRS - Inspection :* |
| 12/22/2004 | BUILDING - FINAL | AMATHIES | Approved | IVRS - Inspection :* 1) OK FOR TEMP C OF O |
| 12/23/2004 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | CLEAR |
| 12/23/2004 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection :*/1)UNISEX RESTROOM IS IN WORKING ORDER 2)OK FOR TEMP C/O |
| 12/23/2004 | ELECTRIC - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |
| 12/23/2004 | ENGINEERING - FINAL | JSALINE | Approved | TEMPORARY C OF O APPROVED. FINAL C OF O CAN BE ISSUED AFTER A FINAL GRADING INSPECTION HAS BEEN REQUESTED, INSPECTED AND APPROVED. |
| 12/23/2004 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 12/23/2004 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection :*/NOT READY FOR INSPECTION |
| 12/29/2004 | ELECTRIC - ABOVE CEILING | RSUBA | Approved | IVRS - Inspection :* 1) LUNCH ROOM, RECEPTION ROOM, VESTIBULE SOUTHEAST, SECURITY VESTIBULE AND LAUNDRY ROOM |
| 12/30/2004 | FIRE - FINAL | LTHOMAS | Approved | Approved for Temporary C of O |
| 12/30/2004 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 12/30/2004 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection :* |
| 01/07/2005 | BUILDING - PROGRESS | AMATHIES | Approved | IVRS - Inspection :* |
| 01/07/2005 | BUILDING ABOVE CEILING | AMATHIES | Approved | IVRS - Inspection :* |
| 01/10/2005 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :*OK FOR C OF O |
| 01/12/2005 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
| 01/19/2005 | PLUMBING - ABOVE CEILING | TRINIVJR | Approved | |
| 04/26/2005 | PERMIT FINALED | LJACKSON | Approved |