Permit: T04CM02901
Permit Details
Apply Date:
06/23/2004
Applicant:
N/A
Description:
NEW:WAREHOUSE SHELL
Architects:
- LEE, LYO TERRELL
Contractors:
- D R I PARTNERS INC
Permit Reviews
Permit Number - T04CM02901
Permit Status: Final
Permit Description: NEW:WAREHOUSE SHELL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/23/2004 | PLANS OK TO SUBMIT - 3RD PARTY | 06/24/2004 | COMPLETED |
06/24/2004 | 3RD PARTY REVIEW-COMMERCIAL | 07/30/2004 | COMPLETED |
07/30/2004 | POST 3RD PARTY REVIEW | 08/31/2004 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T04CM02901
Permit Status: Final
Permit Description: NEW:WAREHOUSE SHELL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/23/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T04CM02901
Permit Description: NEW:WAREHOUSE SHELL
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/13/2004 | ELECTRIC - UFER | JORTA | Approved | IVRS - Inspection :* |
10/13/2004 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :*/TILT UP PERIMETER |
10/19/2004 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection :* |
11/17/2004 | ELECTRIC - UNDERGROUND | RMAJUTA | Approved | UNDERGROUND WEST WALL 2-3/4" PVC'S OK TO COVER |
11/17/2004 | ELECTRIC - INTERMEDIATE | RMAJUTA | Approved | IVRS - Inspection :* |
11/30/2004 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection :* |
12/07/2004 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
12/07/2004 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
12/09/2004 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :* 1) CLOSURE POUR OK |
02/16/2005 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* REVISED PLAN ON SITE APPROVED 1 1/4 H20 OK |
02/16/2005 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
03/01/2005 | ELECTRIC - CABLE DROP | RSUBA | Approved | IVRS - Inspection :* 1) OK TO CLEAR |
03/04/2005 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* APPROVED |
03/04/2005 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
03/10/2005 | OUTDOOR LIGHTING FINAL | RSUBA | Approved | |
03/10/2005 | ELECTRIC - FINAL | RSUBA | Approved | IVRS - Inspection :* APPROVED |
03/10/2005 | FRAMING | LHANLY | Approved | IVRS - Inspection :* |
04/15/2005 | TEP CLEARANCE - PM | JKOZUCH | Approved | ECO PER GERARDO SENT TO TEP AT 3:02PM |
04/27/2005 | FIRE - FINAL | LTHOMAS | Approved | |
04/27/2005 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
04/27/2005 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
05/26/2005 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection :* |
09/28/2005 | PERMIT FINALED | DROBEY | Approved |