Permit: T04CM02620
Permit Details
Apply Date:
06/09/2004
Applicant:
CAPITAL CONSTRUCTION L L C ,
Description:
TOWNHOUSE:TD#11-95-09
Contractors:
- CAPITAL CONSTRUCTION L L C ,
Permit Reviews
Permit Number - T04CM02620
Permit Status: Final
Permit Description: TOWNHOUSE:TD#11-95-09
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/09/2004 | RESIDENTIAL BLDG-MODEL PLAN/ENGINE/WALK THRU | 06/10/2004 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T04CM02620
Permit Status: Final
Permit Description: TOWNHOUSE:TD#11-95-09
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/09/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T04CM02620
Permit Description: TOWNHOUSE:TD#11-95-09
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/14/2004 | PLUMBING - SEWER HCS CONNECT | TRINIVJR | Approved | IVRS - Inspection :*/ 1) SOIL WTR TEST IS OK. 2) HCS CONNECTION IS OK. 3) OK TO BACKFILL TRENCH. |
| 06/14/2004 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | IVRS - Inspection :* |
| 06/14/2004 | BUILDING PRE-SLAB | AMATHIES | Approved | IVRS - Inspection :* |
| 06/14/2004 | EXCAVATION/LAYOUT REBAR & ZON | AMATHIES | Approved | IVRS - Inspection :* |
| 06/22/2004 | PLUMBING - INTERMEDIATE | TRINIVJR | Approved | IVRS - Inspection :*/ 1) SOIL WTR TEST IS OK. 2) OVERHEAD WTR DISTRIBUTION IS OK. |
| 06/22/2004 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 06/22/2004 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
| 06/22/2004 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection :* |
| 06/22/2004 | FRAMING | AMATHIES | Approved | IVRS - Inspection :* |
| 06/22/2004 | ROOF NAILING | AMATHIES | Approved | IVRS - Inspection :* |
| 06/22/2004 | EXT METAL CLIPS/EXT SHEATHING | AMATHIES | Approved | IVRS - Inspection :* |
| 07/19/2004 | ELECTRIC - UFER | DSANTACR | Approved | |
| 07/19/2004 | ELECTRIC - CABLE DROP | DSANTACR | Approved | |
| 07/19/2004 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | IVRS - Inspection :* ok to clear ok ufer |
| 07/19/2004 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 07/20/2004 | TEP CLEARANCE - AM | JKOZUCH | Approved | |
| 07/22/2004 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
| 07/22/2004 | BUILDING - FINAL | AMATHIES | Approved | IVRS - Inspection :* |
| 07/23/2004 | PLUMBING - YARD WTR LINE/TEST | TRINIVJR | Approved | |
| 07/23/2004 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection :* |
| 07/28/2004 | PERMIT FINALED | AMATHIES | Approved |