Permit: T04CM01952
Permit Details
Apply Date:
04/30/2004
Applicant:
PHRED BARTHOLOMAEI
Description:
ADDITION:SPLASH PARK MASONRY WALLS AND SUNSCREEN
Contractors:
- OLLANIK CONSTRUCTION CO INC ,
Permit Reviews
Permit Number - T04CM01952
Permit Status: Final
Permit Description: ADDITION:SPLASH PARK MASONRY WALLS AND SUNSCREEN
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/09/2004 | PLANS OK TO SUBMIT - COMM | 05/03/2004 | COMPLETED |
06/07/2004 | 3RD PARTY REVIEW-COMMERCIAL | 06/11/2004 | COMPLETED |
06/11/2004 | POST 3RD PARTY REVIEW | 06/16/2004 | COMPLETED |
09/24/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 09/29/2004 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T04CM01952
Permit Status: Final
Permit Description: ADDITION:SPLASH PARK MASONRY WALLS AND SUNSCREEN
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/30/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T04CM01952
Permit Description: ADDITION:SPLASH PARK MASONRY WALLS AND SUNSCREEN
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/19/2005 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |
04/25/2005 | ELECTRIC - UFER | MCAPISTR | Approved | IVRS - Inspection :* |
05/26/2005 | ELECTRIC - UNDERGROUND | MCAPISTR | Approved | IVRS - Inspection :* |
06/16/2005 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* |
06/17/2005 | TEP CLEARANCE - AM | JKOZUCH | Approved | ECO TRANS ADDRESSED AS 3700 N ALVERNON |
06/25/2005 | REINFORCED MASONRY PRE-GROUT | BSTEVENS | Approved | |
06/28/2005 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* 1) POOL RPPBP CERTIFICATION ON FILE WITH TUCSON WATER 2) PLUMBING FINAL OK. 3) OK FOR C OF O PENDING ANY OTHER INSPECTIONS. |
06/28/2005 | ELECTRIC - PROGRESS | MCAPISTR | Approved | IVRS - Inspection :* |
06/28/2005 | ELECTRIC - ABOVE CEILING | MCAPISTR | Approved | IVRS - Inspection :* |
06/28/2005 | ELECTRIC - FINAL | MCAPISTR | Approved | IVRS - Inspection :* |
06/28/2005 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
06/28/2005 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* |
06/28/2005 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
06/28/2005 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
06/28/2005 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
06/28/2005 | FIRE - FINAL | LTHOMAS | Approved | |
06/29/2005 | STEM WALL/RETAINING WALL | BSTEVENS | Approved | |
06/29/2005 | BUILDING PRE-SLAB | BSTEVENS | Approved | |
06/29/2005 | ENGINEERING - FINAL | MRUSSO | Approved | C OF O APPROVED |
06/29/2005 | BUILDING - FINAL | BSTEVENS | Approved | IVRS - Inspection :* |
06/29/2005 | BUILDING - PROGRESS | BSTEVENS | Approved | IVRS - Inspection :* |
06/29/2005 | FRAMING | BSTEVENS | Approved | IVRS - Inspection :* |
06/30/2005 | RIGHT OF WAY - FINAL | MOTERO | Approved | |
10/25/2007 | SIGN - FINAL | JYBARRA | Approved | SIGNS HAVE SINCE BEEN REMOVED; OK TO FINAL; SPOKE W/ DALE 349-4268 |
10/30/2007 | PERMIT FINALED | LJACKSON | Approved |