Permit: T04CM01490
Permit Details
Status:
Final
Type:
SINGLE FAMILY ADDITION
Address:
4960 E CALLE JABALI
Address NEW:
4960 E CALLE JABALI
Apply Date:
03/31/2004
Applicant:
O'BRIEN BUILDERS , ALBERT SANTA CRUZ
Description:
ADDITION:GARAGE AND BATHROOM
Contractors:
- O'BRIEN BUILDERS ,
Permit Reviews
Permit Number - T04CM01490
Permit Status: Final
Permit Description: ADDITION:GARAGE AND BATHROOM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/31/2004 | PLANS OK TO SUBMIT - RES | 03/31/2004 | COMPLETED |
| 03/31/2004 | RESIDENTIAL BLDG/WWM | 05/05/2004 | COMPLETED |
| 05/24/2004 | RESUBMITTAL | 06/11/2004 | COMPLETED |
| 06/18/2004 | RESUBMITTAL | 06/18/2004 | COMPLETED |
| 08/17/2004 | REVISION | 08/17/2004 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T04CM01490
Permit Status: Final
Permit Description: ADDITION:GARAGE AND BATHROOM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/31/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T04CM01490
Permit Description: ADDITION:GARAGE AND BATHROOM
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/29/2004 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | IVRS - Inspection :* |
| 06/29/2004 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
| 06/30/2004 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | IVRS - Inspection :* |
| 07/28/2004 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 08/02/2004 | ELECTRIC - SERVICE UPGRADE | DQUINN | Approved | IVRS - Inspection :* |
| 08/03/2004 | TEP CLEARANCE - AM | JKOZUCH | Approved | INC |
| 08/13/2004 | MECHANICAL - INTERMEDIATE | JRIVA | Approved | IVRS - Inspection :* |
| 08/13/2004 | ELECTRIC - INTERMEDIATE | JRIVA | Approved | IVRS - Inspection :* |
| 08/13/2004 | FRAMING | JRIVA | Approved | IVRS - Inspection :* |
| 08/18/2004 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | IVRS - Inspection :* |
| 08/20/2004 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 08/20/2004 | STUCCO MESH | DQUINN | Approved | IVRS - Inspection :* |
| 08/24/2004 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 10/22/2004 | BUILDING - FINAL | DQUINN | Approved | IVRS - Inspection : See detailed listing on site.| 999*/ 1) #1 NOT DONE |
| 10/22/2004 | MECHANICAL - FINAL | DQUINN | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 10/22/2004 | PLUMBING - FINAL | DQUINN | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 10/22/2004 | ELECTRIC - FINAL | DQUINN | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 01/18/2018 | PLUMBING - SEWER HCS CONNECT | NORTH | Approved | |
| 01/18/2018 | EXT METAL CLIPS/EXT SHEATHING | NORTH | Approved | |
| 01/18/2018 | REINFORCED MASONRY PRE-GROUT | NORTH | Approved |