Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T03CM04905
Permit Details
Apply Date:
10/10/2003
Applicant:
MORROW, KEVIN THOMAS
Description:
TI:RETAIL
Contractors:
- TRIUMPH BUILDERS SOUTHWEST LLC *C*
Permit Reviews
Permit Number - T03CM04905
Permit Status: C of o
Permit Description: TI:RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/10/2003 | PLANS OK TO SUBMIT - 3RD PARTY | 10/10/2003 | COMPLETED |
10/14/2003 | 3RD PARTY REVIEW-COMMERCIAL TI | 10/17/2003 | COMPLETED |
10/27/2003 | 3RD PARTY REVIEW-COMMERCIAL | 11/04/2003 | COMPLETED |
11/05/2003 | 3RD PARTY REVIEW-COMMERCIAL | 11/06/2003 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T03CM04905
Permit Status: C of o
Permit Description: TI:RETAIL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/10/2003 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T03CM04905
Permit Description: TI:RETAIL
Total Completed Inspections - 38
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/10/2003 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection 0000*/ 1) ABS DWV UNDERGROUND OK. WATER TEST ONE RISER TO TEN FEET. 2) WATER SERVICE UNDERSLAB TYPE 'K' WITH SIL -FOS'D JOINTS OK. 100# TEST OK. 3) OK TO COVER. |
11/18/2003 | PLUMBING - GAS PRESSURE TEST | TRINIVJR | Approved | IVRS - Inspection 0000*/ 1) GAS PRESSURE TEST IS OK 2) OVERHEAD WATER DISTRIBUTION TO HOSE BIBS ARE OK 3) OK FOR GRID AND TILE |
11/19/2003 | PLUMBING - GAS PRESS TEST FNL | TRINIVJR | Approved | IVRS - Inspection 0000*/ 1) FINAL CONNECTIONS TO GAS PACKS ON ROOF IS OK. 2) GAS PRESSURE TEST IS OK. |
11/20/2003 | PLUMBING - TEMP POWER FOR TEST | TRINIVJR | Approved | |
11/21/2003 | MECHANICAL - TEMP PWR FOR TEST | CWILLIAM | Approved | |
11/21/2003 | BUILDING - TEMP POWER FOR TEST | AMATHIES | Approved | |
11/24/2003 | PLUMBING - INTERMEDIATE | TRINIVJR | Approved | 1) HCS SEWER MAIN TAP IS OK 2) P.OC. OF NEW BLDG SEWER TO EXISTING BLDG DRAIN IS OK 3) OK TO BACKFILL TRENCH |
11/24/2003 | ELECTRIC - TEMP POWER FOR TEST | RMAJUTA | Approved | SENT TO TEP ON 1125AM |
11/24/2003 | BUILDING ABOVE CEILING | AMATHIES | Approved | IVRS - Inspection 0000* |
11/24/2003 | REINFORCED MASONRY PRE-GROUT | AMATHIES | Approved | IVRS - Inspection 0000* |
11/25/2003 | FRAMING | AMATHIES | Approved | IVRS - Inspection 0000* |
11/26/2003 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
11/28/2003 | STUCCO MESH | AMATHIES | Approved | IVRS - Inspection 0000* |
12/02/2003 | PLUMBING - BACK WATER VALVE | TRINIVJR | Approved | IVRS - Inspection 0000*/ BACK WATER VALVE NOT REQUIRED. |
12/02/2003 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection 0000* |
12/02/2003 | SHEET ROCK NAILING | AMATHIES | Approved | IVRS - Inspection 0000* |
12/03/2003 | RIGHT OF WAY - FINAL | MOTERO | Approved | |
12/03/2003 | FIRE - FINAL | JEGAN | Approved | IVRS - Inspection 0000*/ 1) OK FOR C OF O |
12/03/2003 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection 0000* |
12/04/2003 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection 0000*/ PLBG FINAL IS OK. 2) OK FOR C OF O. |
12/15/2003 | SIGN - FINAL | JYBARRA | Approved | |
12/15/2003 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection 0000* |
12/15/2003 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection 0000* |
12/15/2003 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection 0000* |
12/15/2003 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection 0000* |
12/15/2003 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection 0000* |
12/16/2003 | PERMIT FINALED | AMATHIES | Approved | |
12/16/2003 | ENGINEERING - FINAL | JSALINE | Approved | C OF O APPROVED. |
12/16/2003 | ENGINEERING - FINAL | JSALINE | Approved | |
12/16/2003 | PLUMBING - ABOVE CEILING | TRINIVJR | Approved | |
12/16/2003 | BUILDING - FINAL | AMATHIES | Approved | |
12/16/2003 | U VALUE FOR WINDOW | AMATHIES | Approved | |
12/16/2003 | ROOF NAILING | AMATHIES | Approved | |
12/16/2003 | EXT METAL CLIPS/EXT SHEATHING | AMATHIES | Approved | |
12/16/2003 | BUILDING PRE-SLAB | AMATHIES | Approved | |
12/16/2003 | STEM WALL/RETAINING WALL | AMATHIES | Approved | |
12/16/2003 | EXCAVATION/LAYOUT REBAR & ZON | AMATHIES | Approved | |
12/17/2003 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection 0000* |