Permit: T03CM03410
Permit Details
Status:
C of o
Type:
MULTI FAMILY NEW
Address:
6790 E CALLE LA PAZ 02
Address NEW:
6790 E CALLE LA PAZ 02
Apply Date:
07/11/2003
Applicant:
METRO PERMIT EXPRESS, INC
Description:
NEW:APARTMENTS TYPE I
Architects:
- ACORN, KIM BRIAN
Contractors:
- PREFERRED APARTMENT BUILDERS INC
Permit Reviews
Permit Number - T03CM03410
Permit Status: C of o
Permit Description: NEW:APARTMENTS TYPE I
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/08/2004 | 3RD PARTY REVIEW-COMMERCIAL | 04/26/2004 | COMPLETED |
| 04/23/2004 | POST 3RD PARTY REVIEW | 06/11/2004 | COMPLETED |
| 06/11/2004 | RESUBMITTAL | 06/18/2004 | COMPLETED |
| 07/11/2003 | PLANS OK TO SUBMIT - 3RD PARTY | 07/15/2003 | COMPLETED |
| 07/17/2003 | 3RD PARTY REVIEW-COMMERCIAL | 08/12/2003 | COMPLETED |
| 07/20/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 07/30/2004 | COMPLETED |
| 08/20/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 08/23/2004 | COMPLETED |
| 08/31/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 08/31/2004 | COMPLETED |
| 11/09/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 11/15/2004 | COMPLETED |
| 12/07/2004 | POST 3RD PARTY REVIEW | 12/09/2004 | COMPLETED |
| 12/08/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 12/09/2004 | COMPLETED |
| 12/15/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 12/15/2004 | COMPLETED |
| 12/17/2003 | 3RD PARTY REVIEW-COMMERCIAL | 12/29/2003 | COMPLETED |
| 12/27/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 01/05/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T03CM03410
Permit Status: C of o
Permit Description: NEW:APARTMENTS TYPE I
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/11/2003 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T03CM03410
Permit Description: NEW:APARTMENTS TYPE I
Total Completed Inspections - 40
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/02/2004 | PLUMBING - ROUGH, SOIL | JSTANLEY | Approved | IVRS - Inspection :*/PA-OK BLDG @12 CALL FOR INSP & WATER STUBS |
| 01/13/2005 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection :* OK 2 2/0 TO REBAR |
| 01/14/2005 | BUILDING PRE-SLAB | BSTEVENS | Approved | IVRS - Inspection :*APPROVED. |
| 01/14/2005 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | IVRS - Inspection :*APPROVED. |
| 01/18/2005 | PLUMBING - YARD WTR LINE/TEST | JSTANLEY | Approved | IVRS - Inspection :*/ALSO HCS OK |
| 01/19/2005 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | 6"HCS CONNECTION OK |
| 02/28/2005 | ROOF NAILING | BSTEVENS | Approved | IVRS - Inspection :* |
| 05/04/2005 | EXT METAL CLIPS/EXT SHEATHING | BSTEVENS | Approved | IVRS - Inspection :* |
| 05/17/2005 | PLUMBING - ROOF DRAINS | JSTANLEY | Approved | IVRS - Inspection :* |
| 06/02/2005 | FRAMING | BSTEVENS | Approved | IVRS - Inspection :* |
| 07/08/2005 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
| 07/08/2005 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
| 07/19/2005 | U VALUE FOR WINDOW | HLEYVA | Approved | |
| 07/19/2005 | STUCCO MESH | HLEYVA | Approved | |
| 07/19/2005 | BUILDING ABOVE CEILING | HLEYVA | Approved | |
| 08/04/2005 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* OK FOR SHEETROCK |
| 08/04/2005 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
| 08/04/2005 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
| 08/08/2005 | SHEET ROCK NAILING | HLEYVA | Approved | |
| 10/20/2005 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 10/20/2005 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection :*PLBG FINAL IS OK OK FOR C OF O |
| 10/21/2005 | ELECTRIC - TEMP POWER FOR TEST | RSUBA | Approved | IVRS - Inspection :* |
| 10/24/2005 | TEP CLEARANCE - AM | JKOZUCH | Approved | ECO HP5, 2101 THRU 2108 & 2201 THRU 2208 |
| 11/09/2005 | FIRE - FINAL | LTHOMAS | Approved | |
| 11/09/2005 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 11/09/2005 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 11/09/2005 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 11/09/2005 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 11/10/2005 | NPPO - FINAL | ACONNOR | Approved | OK for Temp. C of O. |
| 11/10/2005 | LANDSCAPE - FINAL | ACONNOR | Approved | OK for Temp. C of O. |
| 11/10/2005 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 11/12/2005 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 11/12/2005 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 11/12/2005 | ELECTRIC - CABLE DROP | RHOLLAND | Approved | IVRS - Inspection :* |
| 11/12/2005 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* |
| 11/14/2005 | ENGINEERING - FINAL | JBRUCKME | Approved | TEMPORARY C OF O APPROVED 1. NO MORE TEMPORARY C OF O'S WILL BE GRANTED FOR THIS PROJECT UNTIL THE CITY OF TUCSON RECEIVES A LETTER OF CERTIFICATION FROM THE ENGINEER OF RECORD THAT THE PROJECT WAS CONSTRUCTED IN SUBSTANTIAL CONFORMANCE WITH THE APPROVED PLANS (SEE NOTE 21 OF THE GRADING PLAN). 2. SUBMIT A REVISED GRADING PLAN TO THE CITY OF TUCSON ENGINEERING AND ZONING DIVISIONS FOR REVIEW AND APPROVAL (SEE NOTE 8 OF THE GRADING PLAN). 3. AFTER COMPLETING ITEMS 1 & 2 ABOVE CALL FOR FINAL GRADING INSPECTION #09190 FOR PERMIT #T03BU03223. 4. PROVIDE A LETTER OF CERTIFICATION FROM THE ENGINEER OF RECORD REGARDING THE RETENTION/DETENTION BASIN CONSTRUCTION, DESIGN AND OPERATION (SEE NOTE #31 OF THE GRADING PLAN). 5. STRIPE CROSSWALKS ACROSS ENTRANCE DRIVES. |
| 11/15/2005 | BUILDING - FINAL | JCAGLE | Approved | IVRS - Inspection :*OK FOR T C OF O |
| 11/15/2005 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | Temp Only water valves to be adjusted PER EMAIL |
| 04/12/2006 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | PER MECH FINAL |
| 04/12/2006 | PERMIT FINALED | LJACKSON | Approved |