Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T03CM02601
Permit Details
Apply Date:
05/29/2003
Applicant:
N/A
Description:
ADDITION TO CREMATORY & INSTALL:FURNACE
Contractors:
- R H D CONSTRUCTION L L C ,
Permit Reviews
Permit Number - T03CM02601
Permit Status: Closed
Permit Description: ADDITION TO CREMATORY & INSTALL:FURNACE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/29/2003 | PLANS OK TO SUBMIT - COMM | 05/29/2003 | COMPLETED |
| 05/30/2003 | OTHER | 06/20/2003 | COMPLETED |
| 08/08/2003 | RESUBMITTAL | 09/02/2003 | COMPLETED |
| 09/25/2003 | RESUBMITTAL | 10/17/2003 | COMPLETED |
| 10/20/2003 | RESUBMITTAL | 10/21/2003 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T03CM02601
Permit Status: Closed
Permit Description: ADDITION TO CREMATORY & INSTALL:FURNACE
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 05/29/2003 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 06/18/2003 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. |
| 06/18/2003 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
Outstanding Inspections
Permit Status: Closed
Permit Number: T03CM02601
Permite Description: ADDITION TO CREMATORY & INSTALL:FURNACE
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| OUTDOOR LIGHTING FINAL | N/A | Not Inspected | ||
| MECHANICAL - INTERMEDIATE | N/A | Not Inspected | ||
| 01/21/2004 | ELECTRIC - INTERMEDIATE | N/A | Partial Approval | IVRS - Inspection 0000* |
Completed Inspections
Permit Status: Closed
Permit Number: T03CM02601
Permit Description: ADDITION TO CREMATORY & INSTALL:FURNACE
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/22/2003 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection 0000*/ 1) GAS PRESSURE TEST IS OK 2) NOTE: THIS INSPECTION IS FOR 2" GAS LINE FOR NEW FURNACE 3) FINAL INSPECTION IS NOT READY |
| 10/22/2003 | PLUMBING - GAS PRESSURE TEST | TRINIVJR | Approved | IVRS - Inspection 0000* |
| 10/22/2003 | PLUMBING - INTERMEDIATE | TRINIVJR | Approved | IVRS - Inspection 0000* |
| 10/29/2003 | EXCAVATION/LAYOUT REBAR & ZON | AMATHIES | Approved | IVRS - Inspection 0000* SOLID BLOCK AT WALL LINE |
| 11/18/2003 | BUILDING PRE-SLAB | AMATHIES | Approved | IVRS - Inspection 0000* |
| 11/18/2003 | STEM WALL/RETAINING WALL | AMATHIES | Approved | IVRS - Inspection 0000* |
| 12/19/2003 | REINFORCED MASONRY PRE-GROUT | AMATHIES | Approved | IVRS - Inspection 0000* |
| 01/21/2004 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection 0000*/ 1) OK TO CLEAR-INCREASE 2) BLDG HAS POWER NOW FROM EXISTING SERVICE 3) SENT TO TEP ON 01/22/04AM |
| 03/18/2004 | BUILDING - FINAL | AMATHIES | Approved | |
| 03/18/2004 | FRAMING | AMATHIES | Approved | |
| 03/18/2004 | ROOF NAILING | AMATHIES | Approved | |
| 02/26/2008 | MECHANICAL - FINAL | LHANLY | Approved | IVRS - Inspection :* |