Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T03CM02421
Permit Details
Apply Date:
05/19/2003
Applicant:
N/A
Description:
NEW RETAIL SHELL:DAVID'S BRIDAL
Contractors:
- CANYON BUILDING AND DESIGN L L C
Permit Reviews
Permit Number - T03CM02421
Permit Status: Final
Permit Description: NEW RETAIL SHELL:DAVID'S BRIDAL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/19/2003 | PLANS OK TO SUBMIT - COMM | 05/19/2003 | COMPLETED |
05/19/2003 | PLANS OK TO SUBMIT - SITE | 05/19/2003 | COMPLETED |
05/20/2003 | COMMERCIAL NEW | 07/22/2003 | COMPLETED |
05/20/2003 | SITE | 07/22/2003 | COMPLETED |
07/25/2003 | RESUBMITTAL - SITE | 07/25/2003 | COMPLETED |
07/25/2003 | RESUBMITTAL | 07/25/2003 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T03CM02421
Permit Status: Final
Permit Description: NEW RETAIL SHELL:DAVID'S BRIDAL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
05/19/2003 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T03CM02421
Permit Description: NEW RETAIL SHELL:DAVID'S BRIDAL
Total Completed Inspections - 39
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/30/2003 | ELECTRIC - UFER | MCAPISTR | Approved | IVRS - Inspection 0000* |
08/04/2003 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection 0000* STEM OK |
09/18/2003 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection 0000*/ OK TO PROCEED. |
09/18/2003 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
09/22/2003 | FRAMING | AQUIROZ | Approved | IVRS - Inspection 0000* |
09/23/2003 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection 0000* |
09/25/2003 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection 0000* |
09/25/2003 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection 0000* |
09/25/2003 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection 0000* |
09/25/2003 | ELECTRIC - UNDERGROUND | RMAJUTA | Approved | IVRS - Inspection 0000* |
10/01/2003 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
10/01/2003 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection 0000* |
10/01/2003 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
10/02/2003 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection 0000* |
10/02/2003 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection 0000* |
10/02/2003 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection 0000* |
10/02/2003 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection 0000* |
10/06/2003 | RIGHT OF WAY - FINAL | MOTERO | Approved | |
10/06/2003 | FIRE SPKLR - OH PIPING & HYDRO | JEGAN | Approved | IVRS - Inspection 0000* |
10/06/2003 | FIRE SPKLR - UG PIPING FLUSH | JEGAN | Approved | IVRS - Inspection 0000* |
10/06/2003 | FIRE SPKLR - UG, PIPING, HYDRO | JEGAN | Approved | IVRS - Inspection 0000* |
10/06/2003 | ELECTRIC - ABOVE CEILING | MCAPISTR | Approved | IVRS - Inspection 0000* |
10/06/2003 | ELECTRIC - INTERMEDIATE | MCAPISTR | Approved | IVRS - Inspection 0000*/ INCLUDES ELECTRIC SERVICE EQUIPMENT. |
10/08/2003 | MECHANICAL - TEMP PWR FOR TEST | CWILLIAM | Approved | |
10/08/2003 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection 0000*/1) REVIEWED ENGINEERS APPROVAL OF SEWER CONNECTION IN MANHOLE. 2) PLUMBING FINAL OK - OK FOR C OF O PENDING OTHER INSPECTIONS. |
10/08/2003 | PLUMBING - TEMP POWER FOR TEST | RMYERS | Approved | |
10/08/2003 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection 0000* |
10/08/2003 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | |
10/08/2003 | ELECTRIC - TEMP POWER FOR TEST | MCAPISTR | Approved | |
10/08/2003 | BUILDING - TEMP POWER FOR TEST | AQUIROZ | Approved | |
10/09/2003 | SIGN - FINAL | JYBARRA | Approved | NO SIGN AT THIS TIME/ SHELL ONLY |
10/15/2003 | FIRE - FINAL | JEGAN | Approved | IVRS - Inspection 0000* |
10/15/2003 | FIRE SPKLR - FINAL | JEGAN | Approved | IVRS - Inspection 0000*/ 1) OK C OF O SHELL BLDG |
10/15/2003 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection 0000* |
10/23/2003 | ELECTRIC - FINAL | MCAPISTR | Approved | IVRS - Inspection 0000* |
12/08/2003 | NPPO - FINAL | PGILBERT | Approved | |
12/08/2003 | LANDSCAPE - FINAL | PGILBERT | Approved | |
12/08/2003 | ENGINEERING - FINAL | JBRUCKME | Approved | TEMPORARY C OF O APPROVED, 1. PERMANENT C OF O NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTION #09190 FOR T02BU01121 IS COMPLETED AND APPROVED. 2. CONTACT CRAIG GROSS (ZONING DIVISION) AND MATT FLICK (ENGINEERING DIVISION) IN REGARDS TO PHASING THE PLAN FOR BUILDINGS 1 AND 2. 3. PROVIDE BICYCLE PARKING AS SHOWN ON THE PLAN OR REVISE PER ZONING REQUIREMENTS. |
12/08/2003 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection 0000* |