Permit Details

Status:
Final
Type:
COMMERCIAL ALTERATION
Apply Date:
03/03/2003
Applicant:
N/A
Description:
TI:OFFICE
Architects:
  • TAYLOR, ROBERT JOHN
Contractors:
  • HAZEN LTD , STEVE

Permit Reviews

Permit Number - T03CM01059
Permit Status: Final
Permit Description: TI:OFFICE
Start Date Submittal Complete Date Status  
03/03/2003 COMMERCIAL TI 03/06/2003 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T03CM01059
Permit Status: Final
Permit Description: TI:OFFICE
Total Outstanding Activity Conditions - 1
Date Name
03/03/2003 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T03CM01059
Permit Description: TI:OFFICE
Total Completed Inspections - 12
Date Description Inspector Results Comments
03/07/2003 ELECTRIC - INTERMEDIATE RHOLLAND Approved IVRS - Inspection 0000*
03/07/2003 SHEET ROCK NAILING RSUBA Approved IVRS - Inspection 0000*
03/07/2003 FRAMING RSUBA Approved IVRS - Inspection 0000*SCREW NAILING
03/14/2003 RIGHT OF WAY - FINAL PWHIDDON Approved
03/14/2003 SIGN - FINAL JYBARRA Approved IVRS - Inspection 0000*
03/14/2003 ENGINEERING - FINAL JBRUCKME Approved
03/14/2003 FIRE - FINAL JEGAN Approved IVRS - Inspection 0000*
03/14/2003 ELECTRIC - FINAL RHOLLAND Approved IVRS - Inspection 0000*OK FINAL.
03/14/2003 ELECTRIC - ABOVE CEILING RHOLLAND Approved IVRS - Inspection 0000*
03/17/2003 PERMIT FINALED RSUBA Approved
03/17/2003 BUILDING - FINAL RSUBA Approved
03/17/2003 BUILDING - FINAL RSUBA Approved IVRS - Inspection 0000*

Documents

File Name Document Type  
C OF O_05-09-2003.TIF CERT OF OCC VIEW
None DOCUMENTS VIEW