Permit: T03CM00320
Permit Details
Apply Date:
01/24/2003
Applicant:
GLENN BANCROFT
Description:
APARTMENTS:NEW
Contractors:
- MARK WRIGHT CONSTRUCTION
Permit Reviews
Permit Number - T03CM00320
Permit Status: C of o
Permit Description: APARTMENTS:NEW
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/24/2003 | PLANS OK TO SUBMIT - COMM | 02/14/2003 | COMPLETED |
02/14/2003 | COMMERCIAL NEW | 04/11/2003 | COMPLETED |
02/14/2003 | SITE | 04/11/2003 | COMPLETED |
02/18/2005 | REVISION | 02/18/2005 | COMPLETED |
03/24/2004 | REVISION | 03/25/2004 | COMPLETED |
06/10/2003 | SITE | 07/15/2003 | COMPLETED |
06/10/2003 | RESUBMITTAL | 07/15/2003 | COMPLETED |
08/26/2003 | RESUBMITTAL | 01/27/2004 | COMPLETED |
08/26/2003 | RESUBMITTAL - SITE | 01/27/2004 | COMPLETED |
10/05/2004 | REVISION - SITE | 10/12/2004 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T03CM00320
Permit Status: C of o
Permit Description: APARTMENTS:NEW
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/24/2003 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T03CM00320
Permit Description: APARTMENTS:NEW
Total Completed Inspections - 41
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/29/2004 | PLUMBING - BACK WATER VALVE | JSTANLEY | Approved | IVRS - Inspection 0000* |
03/29/2004 | PLUMBING - BACK WATER VALVE | JSTANLEY | Approved | IVRS - Inspection 0000* |
03/29/2004 | PLUMBING - SEWER HCS CONNECT | JSTANLEY | Approved | IVRS - Inspection 0000*/ NEED TO PROVIDE SEWER AGREEMENT. |
03/29/2004 | PLUMBING - ROUGH, SOIL | JSTANLEY | Approved | IVRS - Inspection 0000* |
04/06/2004 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection 0000*OK 2/0 TO REBAR |
04/06/2004 | BUILDING PRE-SLAB | RSUBA | Approved | IVRS - Inspection :* |
04/06/2004 | EXCAVATION/LAYOUT REBAR & ZON | RSUBA | Approved | IVRS - Inspection :* |
05/16/2004 | ROOF NAILING | HLEYVA | Approved | IVRS - Inspection :*/ 1) FOR BLDG A |
05/26/2004 | EXT METAL CLIPS/EXT SHEATHING | RSUBA | Approved | IVRS - Inspection :* |
06/02/2004 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
06/02/2004 | PLUMBING - YARD WTR LINE/TEST | TRINIVJR | Approved | IVRS - Inspection :*/ 1) YARD WTR LINE FROM METER TO BLDG SERVICE OK. 2) OK TO BACKFILL TRENCH. |
06/17/2004 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
06/17/2004 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :*/ OK FOR SHEET ROCK. |
06/17/2004 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | PRESSURE NOT UP (200) 2) NEED REQUEST FROM CUTLER |
06/17/2004 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
06/17/2004 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :*/ 1) PLEASE PROVIDE FLEX CONDUIT FOR WTR HTR ON ROUGH IN. WE NEED TO INSPECT FOR SUPPORT AND CABLE PROTECTION. 2) ROMEX CONNECTOR TO SECURE CABLES. 3) SUPPORT CABLES ABOVE PANEL. 4) NM CABLE TO BE SUPPORTED WITHIN 12" OK BOX/FITTINGS. OK ROUGH. |
06/17/2004 | U VALUE FOR WINDOW | RSUBA | Approved | IVRS - Inspection :* |
06/17/2004 | STUCCO MESH | RSUBA | Approved | IVRS - Inspection :* |
06/17/2004 | BUILDING ABOVE CEILING | RSUBA | Approved | IVRS - Inspection :* |
06/17/2004 | FRAMING | RSUBA | Approved | IVRS - Inspection :* |
07/01/2004 | PLUMBING - INTERMEDIATE | TRINIVJR | Approved | IVRS - Inspection :*/ LEAK UNDERSLAB WAS REPAIRED. |
07/01/2004 | PLUMBING - PROGRESS | TRINIVJR | Approved | IVRS - Inspection :* |
07/07/2004 | SHEET ROCK NAILING | HLEYVA | Approved | IVRS - Inspection :* |
08/12/2004 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :*/ PLEASE ADD CABLE DROP 02050 AND TEMP PWER FOR TEST 02062 TO PERMIT. |
08/13/2004 | ELECTRIC - TEMPORARY SERVICE | RHOLLAND | Approved | INSTALL PANEL COVERS |
08/13/2004 | ELECTRIC - CABLE DROP | RHOLLAND | Approved | IVRS - Inspection :* |
08/16/2004 | TEP CLEARANCE - AM | JKOZUCH | Approved | CEC |
02/08/2005 | ELECTRIC - TEMP POWER FOR TEST | RMAJUTA | Approved | OK TEMP POWER FOR TEST ON BOND,1101THUR1104,AND 1201 PER HOLLANDER |
02/10/2005 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* OK FOR FINAL |
02/10/2005 | MECHANICAL - PROGRESS | JMILITEL | Approved | |
02/10/2005 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* OK FINAL |
02/15/2005 | PLUMBING - ABOVE CEILING | JSTANLEY | Approved | |
02/15/2005 | PLUMBING - FINAL | JSTANLEY | Approved | IVRS - Inspection :* |
02/15/2005 | FIRE - FINAL | LTHOMAS | Approved | |
02/15/2005 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
02/15/2005 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
02/16/2005 | BUILDING - PROGRESS | BSTEVENS | Approved | |
02/16/2005 | BUILDING - FINAL | BSTEVENS | Approved | IVRS - Inspection :* |
03/24/2005 | LANDSCAPE - FINAL | ACONNOR | Approved | |
04/25/2005 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
04/29/2005 | PERMIT FINALED | LJACKSON | Approved |